We attempt to list all turbines over 30m (100 ft), but this is becoming increasingly difficult.
This is due to the numbers of applications coming forward, fuelled by the very large subsidies paid under the Feed-in Tariff system of subsidies, which are paid from electricity bills.
Many of these applications are not advertised and are often quickly decided by a planning officer under delegated powers, rather than by a democratically accountable planning committee. Many are now decided without an Environmental Impact Assessment.
|
|
|
|
Small/domestic turbines up to c. 30.5m (100 ft) in height are not recorded.
Some output and load factor figures taken from Ofgem’s data are now included. Companies declare output in order to claim tradeable Renewables Obligation Certificates (ROC’s). Lack of figures for a particular year indicates that a full year’s production did not take place. This data is published in more accessible form by REF as a PDF download. (See 'UK Renewable Energy Data').
Total Installed Generating Capacity (TIGC) is given; this is the amount of power the scheme could theoretically generate at peak.
The intermittent nature of wind power means that the actual load factor (aka ‘capacity factor’), or percentage of headline capacity produced, averaged over a year, can be anything between 8% and 40% of the headline figure, depending on the wind resource on site. The wind industry likes to claim that onshore wind turbine arrays usually have a load/capacity factor of 30%; our regional planners assume a figure of 29/30%. The March 2006 issue of ‘Energy Trends’, produced by the Department of Trade and Industry, has a table for onshore wind farms in the UK produced from actual production figures. This table shows that the North East has the lowest recorded load factor in the country: for 2003 the figure was 19%; for 2004 the figure was 21%. The average for 1998-2004 was 21%.
Schemes of 50MW capacity or over - even if they would only produce a fraction of this amount in operation - are determined by a government Minister according to Section 36 of the Electricity Act 1989 (or the equivalent Section 57 of the Town and Country Planning (Scotland) Act 1997). This was originally intended as a mechanism for major projects that were considered to be in the national interest. It is questionable whether it was intended as a mechanism for developers to try and sideline the local democratic planning process with wind power projects having a theoretical maximum capacity of just over 50MW, and which would produce as little as 20% to 30% of that headline capacity in operation.
Some developers regard Section 36 applications as standing more chance - they are, after all, being decided by a Minister who is also responsible for implementing current energy policy - than would smaller schemes with local planners who are more inclined to reflect the concerns of their local communities and the local economy. A public inquiry can be triggered by the formal objection of a local planning authority, but the developers know very well that cash-strapped local authorities and poorly funded community groups are then forced to find large sums of money in order to secure legal representation. At the end of the day, the Secretary of State can, but seldom does, override the inspector’s recommendation.
‘Scoping’ = site investigation, pre-application consultation with planning authority (may involve application to erect an anemometer mast for recording wind speeds, not required by the planning process but needed when raising finance).
‘Proposal of Application Notice (PAN)’ = the Scottish Government has introduced regulations requiring 12 weeks of pre-application [public] consultation (PAC) before lodging a major planning application. A PAN starts the clock on this process.
‘Live Application’ = planning application submitted.
‘Appealed’ = proposals may be appealed by the applicant after refusal or for ‘non-determination’, when the applicant decides to trigger an appeal
because the local planning authority has not determined the application within the prescribed time period (normally 12 weeks). Objectors have no right of appeal if a decision is approved, they can only seek to overturn the decision by going to the High Court (in England) to seek a judicial review of the decision on procedural grounds. This rarely succeeds and can be ruinously expensive if costs are awarded to the company.
‘Called in/Recovered’ = decision removed from a Planning Inspector to the Secretary of State, or Scottish equivalent. There are a number of reasons set out for this action, the last English government started recovering decisions because, “the appeal involves proposals of major significance for the delivery of the Government's climate change programme and energy policies.”
‘PI’ = Public Inquiry; quasi-judicial hearing to examine the application before a Planning Inspector (‘Reporter’ in Scotland). For Section 36 schemes, an objection from the LPA is needed to trigger a PI.
‘Status unclear’ = lapsed, withdrawn, not proceeding etc.
‘LF’ = Load Factor: percentage of headline capacity produced by turbine(s), averaged over a year.
‘LPA’ = Local Planning Authority.
‘NYD’ = Not yet determined.
‘TIGC’ = Total Installed Generating Capacity.
Rejected and lapsed/withdrawn proposals are included below because, even after failure at appeal, they can reappear as slightly adjusted re-submissions. Wind developers are notoriously unwilling to take no for an answer when they have spent some money in working up a proposal. These sites also indicate areas of developer interest.
Title colours match application status: orange - scoping/pre-planning; red - in planning (applied/appealed); green - approved; black - operating; grey - refused, withdrawn, lapsed etc.; a blue background signifies offshore schemes which are not counted in regional capacity targets.
|
|
|
|
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| Aesica Pharmaceuticals | Cramlington | 2 | 110m. | 2.5MW | 5MW | Refused. Appeal withdrawn. |
Applied 5/06 for two 140m turbines (06/00275/ful). Rejected 15.8.06, radar impacts (Newcastle Airport). Re-applied 8/06, two 110m turbines (06/00384/res). Permission refused. Appeal lodged, withdrawn before the hearing. |
|
| Barmoor | Nr. Lowick (NT980380) |
6 | 110.5m | 3MW | 18MW | Catamount/ Force 9 |
Under construction | Refused by LPA (27/03/08). Appeal (May-June 2009). Approved, on Inspector’s recomm., 20/01/10. |
| Belford Burn | Nr. Belford (NU080335) |
9 | 100m | 2.5MW | 22.5MW | Energie Kontor | Pre-application | Next to Middleton Burn. Not in ‘area of least constraint’. Application for 60m anem. mast - Ref. 12/01045/RENE. Response Group: Middleton Burn Action Group (MBAG). |
| ‘Berwick’ | ca. 1.5 km. N. of Halidon Hill | 7 | 120m. | 2MW | 14MW | RES (not listed on website) |
Not yet progressed | |
| Berwick - Steps of Grace | Steps of Grace, north of Ramparts Business Park (NT 986555). | 1 | 74m. | 0.8MW | 0.8MW | Community Renewable Energy Ltd | Consented (07/09/10) |
NCC Planning Ref. C/10/00084/REN. Enercon E48 turbine proposed. ‘Community turbine’: “Berwick’s Community Wind Turbine — using the power of the wind to supply an income for our Community.” (Brochure headline). |
| Berwick - Ramparts Business Park | Ramparts Business Park | 1 | 31m. | ?MW | ?MW | Maden Design and Build | Consented | |
| ‘Bewick Drift’ | Lynemouth (NZ299903) |
3 | 132m (prev. 110m) | 2.5MW (prev. 3MW) | 7.5MW (prev. 9MW) | UK Coal | Consented on appeal (02/08). Consent varied (03/08/10) |
Consent varied to allow use of larger, 130m, Clipper Windpower ‘Liberty’ turbine, a model they are seeking to sell into the British market. One turbine (T3) to be built in the first instance as there are, “outstanding geological and coastal erosion issues associated with turbines T1 and T2” (Officer’s report). Subsequently increased again to 132m (C/11/00002/NMA). |
| Bewick Moor | "2.9 km. SE of Chillingham" | Acciona | Pre-application. | originated by Spanish company EHN (notorious for their Navarre bird killers), now part of the Acciona Group. Anem. Mast (Dec. 2005) now within SSSI, up for 6 years, 3rd. renewal refused (04/12) See press story, 2 May, 2012. |
||||
| Bewick Moor | "3.8 km. NE of Old Bewick" | Acciona | Pre-application. | originated by Spanish company EHN (notorious for their Navarre bird killers), now part of the Acciona Group. Anem. Mast (Dec. 2005) now within SSSI, up for 6 years, 3rd. renewal refused (04/12) See press story, 2 May, 2012 |
||||
| Blyth Harbour | Blyth (NZ322813) |
9 | 42.5m. | 0.3MW | 2.7MW | AMEC | Operating (1993) | WindMaster turbines.
UK’s most unproductive WF. Repowering consented, see below. Blyth Harbour Wind Farm A (R00062RQEN): 2002/3 MWh/ROCs:2,681 LF:11.3% 2003/4 MWh/ROCs:2,347 LF:9.9% 2004/5 MWh/ROCs:3,084 LF:13.0% 2005/6 MWh/ROCs:2,708 LF:11.4% 2006/7 MWh/ROCs:2,582 LF:10.9% 2007/8 MWh/ROCs:2,278 LF:9.6% 2008/9 MWh/ROCs:1,445 LF:6.1% 2009/10 MWh/ROCs:1,169 LF:4.9% 2010/11 MWh/ROCs:715 LF:3.0% Rolling LF: |
| Blyth Harbour (Repowering) |
Blyth (NZ322813) |
7 | 130m | 3.4MW | 23.8MW | Hainsford Energy | Consented (08.01.08) |
Delegated consent to increase height turbines to 130m (March 2011). Proposed 5MW ‘Britannia project’ turbine dropped after Clipper’s failure to meet deadlines on turbine development. First REpower 3.4M104 ordered, installation scheduled mid-2012. |
| Blyth Offshore | Nr. Blyth (NZ325825) |
2 | 93m. | 1.8 & 2MW | 3.8MW | Project Consortium. Sold to E.ON UK June 2007. |
Commissioned 2000. U/S 04.06 - 01.09 |
‘Demonstration project’ built with unspecified financial support from the EU Thermie Programme.
Blade accident on WTG 1, Jan. 2002. Out of service from April 2006 until January 2009 (cable damage). Blyth Offshore WF (R00001RPEN): 2002/3 MWh/ROCs:2,347 2003/4 MWh/ROCs:3,524 LF:20.1% 2004/5 MWh/ROCs:3,997 LF:22.8% 2005/6 MWh/ROCs:517 2006/7 MWh/ROCs:0 2007/8 MWh/ROCs:0 2008/9 MWh/ROCs:1,166 2009/10 MWh/ROCs:3,045 2010/11 MWh/ROCs:2,714 LF:15.5% Rolling LF: Blyth Offshore WTG 2(R00002RPEN): 2008/9 MWh/ROCs:598 2009/10 MWh/ROCs:3,032 LF:17.3% 2010/11 MWh/ROCs:2,350 Rolling LF: |
| Blyth Offshore Wind Demonstrator Project 2 | “Approx. 5.6km from Blyth” | up to 5 | up to 195m | “up to 100MW” for NAREC 2,3 &4. | Narec/Crown Estates/? | Live application (28/03/12) |
“Application made to Marine Management Organisation (MMO), Non-Technical Summary available from Narec website.
Narec’s plans to develop an offshore wind farm site in the North Sea, comprising 15 pre-consented “pods”, at which tenants may deploy their prototype or demonstration turbines and foundations.” |
|
| Blyth Offshore Wind Demonstrator Project 3a | “Approx. 7km from Newbiggin” | up to 5 | up to 195m | “up to 100MW” for NAREC 2,3 &4. | Narec/Crown Estates/? | Live application (28/03/12) |
Application made to Marine Management Organisation (MMO), Non-Technical Summary available from Narec website.
“Narec’s plans to develop an offshore wind farm site in the North Sea, comprising 15 pre-consented “pods”, at which tenants may deploy their prototype or demonstration turbines and foundations.” |
|
| Blyth Offshore Wind Demonstrator Project 3b | “Approx. 13km from Blyth” | up to 5 | up to 195m | “up to 100MW” for NAREC 2,3 &4. | Narec/Crown Estates/? | Live application (28/03/12) |
Application made to Marine Management Organisation (MMO), Non-Technical Summary available from Narec website.
“Narec’s plans to develop an offshore wind farm site in the North Sea, comprising 15 pre-consented “pods”, at which tenants may deploy their prototype or demonstration turbines and foundations.” |
|
| Blyth Offshore Wind Demonstrator Project 4 | “Approx. 14km from Blyth” | up to 5 | up to 195m | “up to 100MW” for NAREC 2,3 &4. | Narec/Crown Estates/? | Live application | “Narec’s plans to develop an offshore wind farm site in the North Sea, comprising 20 pre-consented “pods”, at which tenants may deploy their prototype or demonstration turbines and foundations.”
|
|
| Boundary Lane | Nr. Whittonstall | 3 | 115m* | 2MW | 6MW | EDF | Consented (17/02/11) |
* Application in to vary the consent, increasing height to 115m from 110m. Construction “Spring 2012”. NCC Application No. 09/00092/CCMEIA. |
| Brackenside |
Nr. Lowick | 1 | 47.1m. | 0.1MW | 0.1MW | GF White for Mr John Barber | Consented (02/02/12) |
NCC Planning Ref. 11/02217/FUL. Officer’s report ignored planning history of the site and cumulation issues |
| Bridge Mill |
Nr. Haggerston (E402932 N644212) |
1 | 46m. | 0.05MW | 0.05MW | GF White for Messrs D T Wright | Live application (14/12/11) |
NCC Planning Ref. 11/03277/RENE . Endurance E-3120 turbine. |
| The Brocks | Nr. Longhirst | 1 | 77.9m | 0.5MW | 0.5MW | Pre-application | NCC screening opinion (11/00814/PREAPP). |
|
| Butterwell |
Nr. Longhirst | 9 | 125m. | 2.3MW | 20.7MW | RES, not on website | Pre-application | (aka ‘Bluberry Wood’). Next to Novera’s withdrawn Longhirst proposal. Then LPA rejected 80m Anem. Mast application (3/06), approved for 3 yrs.on appeal (12/06). Another 3 yrs. approved. |
| Coat Yards Farm | Nr. Longhorsley | 5 | 125m. | 3MW | 15MW | Coronation Power | ‘Dropped after scoping’ | |
| Currock Hill/Hedley-on-the-Hill | Nr. Hedley-on-the-Hill | 6 (2x3) |
140m. | ? | ? | Pure Renewable Energy | Pre-application | See Hexham Courant 25.01.08 |
| Debdon Farm | Nr. Rothbury | 8 | ? | 3MW | 24MW | West Coast Energy Limited. | Mast rejected. |
Anem. Mast refused 8/07 (‘visually intrusive’). |
| Earth Balance. | Land NE Of Earth Balance, Bedlington (E427463 N584637) |
1 | 70m | 0.33MW | 0.33MW | North Energy Associates for Blue Energy Wind Ltd | Live application (27/02/12) |
NCC planning ref. 12/00385/RENE. Enercon E33 turbine proposed. |
| East Coldcotes | Nr. Ponteland (NZ153750) |
1 | 77.9m. | 0.5MW | 0.5MW | George F White for ‘Green Energy Ponteland’ Ltd. | Refused (06/12/11) |
Decisively rejected (9:2), against officer recommendation. NCC Planning Ref. 11/01733/RENE. Green Energy Ponteland Ltd is registered to Louis Fell, a partner in George F White, the agents in this proposal. |
| East House Farm | Nr. Warkworth | ? | ?m | ?MW | ?MW | Empirica Investments | Pre-application | |
| East Moneylaws. | Nr. Branxton (E387833 N636025) |
2 | 34.2m | 0.05MW | 0.1MW | Maden Design & Build for Mr Robin Lathangie | Live application (05/01/12) |
NCC planning ref. 11/03207/RENE . Endurance E-3120 turbines. |
| East Wingates | Nr. Wingates | 6 | 100m | 2.00-2.5MW | 12 to 15MW | BT | “Not progressed” | Split site, 3 turbines at Wingates Moor refused. BT say, “BT will not be progressing with a separate wind farm proposal for East Wingates wind farm, just to the east of Wingates village. After thorough assessment and consultation BT considers that this site would not be suitable due to potential impacts on the local community in combination with other wind farm sites in the area.” (BT Website). Local response group: Wingates NOT Wind Farms (WNWF). |
| East Newbiggin (“Land South East Of Viaduct”). | Nr. Norham (E390323 N645924) |
1 | 54m | 0.25MW | 0.25MW | Carleton Border Services for Mr Ian Martin, Galagate Farms | Withdrawn (10/01/12) |
Resubmission expected. NCC planning ref. 11/02948/RENE. WES30 turbine. Mirrors Fellowhills application, near Ladykirk, for same landowner (see Scottish Borders entry). |
| Fenrother | Nr. Longhorsley | 5 | 126m | ?MW | ?MW | Energiekontor (not listed on website) |
Pre-application | Preliminary developer exhibitions: Tritlington C of E First School, Wed. 13 Oct., 5-8pm. Longhorsley Vill. Hall, Thurs. 14 Oct. 5-8pm. Local response group: Fight Fenrother Wind Farm. |
| Fergusons Bus. Pk. West | Nr. Bedlington (E427463 N584637) |
1 | 77m | 0.5MW | 0.5MW | North Energy Associates for Blue Energy Wind Ltd | Live application (21/02/12) |
NCC planning ref. 12/00375/RENE . EWT Directwind 54 turbine proposed. |
| Gapshield | Nr. Greenhead | 5 | ? | 2.1MW | 10.5MW | RES (not listed on website) |
Pre-application | |
| Green Rigg | Nr. Sweethope Lough | 18 | 110m. | 2MW | 36MW | Wind Prospect | Under construction. Consented on appeal (25/03/10). |
Joint public inquiry (+ Ray & Steadings) 2008. Consented by Secretary of State (25/03/2010), subject to conditions. See: Inspector’s Report (large PDF file) and Decision letter (PDF file). |
| Gubeon Farm | Nr. Morpeth | 1 | ?53m | 0.33MW | 0.33MW | Pre-application | NCC screening opinion for 87.5m Enercon E53 turbine (12/00117/PREAPP), 10/02/12; followed by screening opinion for smaller turbine (date not given). |
|
| Hadston | Nr. Hadston, Broomhill & Togston. | ? | ?m | ?MW | ?MW | Hadston Wind Farm Future Electric (Hadston) Ltd. Future Electric Ltd |
Pre-application | Close to Druridge Country Park. |
| Hexham Racecourse | High Yarridge, Nr. Hexham (E391928 N562240) |
1 | 51m (Envelope) | 0.225MW | 0.225MW | North Energy for Hexham Racecourse | Live application (26/01/12) |
NCC planning ref.11/03400/RENE. ACSA A29 turbine proposed (46.9m). |
| High Cowden Farm | Birtley, Nr. Hexham (E391827 N579320) |
1 | 45.45m | 0.225MW | 0.225MW | AAH Planning Consultants for landowner | Live application (27/10/11) |
NCC planning ref. 11/02484/FUL. ACSA A27 turbine proposed. NCC planners understate height by using hub height (32m), not the blade tip height (45.5m). |
| Kielder | Kielder | Unclear | Still described as ‘strategic resource area’ in some circles. Talks ongoing (?) with MOD on radar constraints. |
|||||
| Kielder (Humble Hill) |
Kielder | 100 | 80m | EcoGen | Refused DTI Upheld at jud. rev. |
Section 36 Application to DTI/DBERR (Over 50MW) Originally seen as being in ‘Strategic resource area’. Talks ongoing (?) with MOD on radar constraints. Also within the proposed exclusion zone for the Eskdalemuir seismological recording station (see maps). |
||
| Kiln Pit Hill | Nr. Slaley | 6 | 120m | 2MW | 12MW | NPower | Consented on appeal (12/2/09) |
Inspector rejected both Arup and listed buildings protection. See: Appeal Decision (PDF document). |
| Kirkharle | Bavington Hillhead, nr. Kirkharle (NY995805) |
4 | 125m. | 3MW | 12MW | NPower | Appeal refused (04/11/11) |
Appealed for non-determination. Another 4 turbines at Bavington Northside withdrawn. Appeal refused: decision doc). |
| Kirkheaton | Kirkheaton, nr. Hexham (NZ009770) |
3 | 66.5m. | 0.6MW | 1.8MW | EDF | Commissioned 2000 |
Nordex turbines.Blades removed on 2 turbines due to faults; U/S since Autumn 2008. Non-op. turbines should be removed after a set period but NCC has twice granted a variation of the planning condition to permit the non-op. for a year.
Kirkheaton WF (R00020RQEN): 2002/3 MWh/ROCs:3,793; LF:24.1% 2003/4 MWh/ROCs:4,044; LF:25.6% 2004/5 MWh/ROCs:3,997; LF:25.3% 2005/6 MWh/ROCs:3,653; LF:23.2% 2006/7 MWh/ROCs:4,907; LF:31.1% 2007/8 MWh/ROCs:3,747; LF:23.7% 2008/9 MWh/ROCs:1,694; LF:10.7% [2 turbines U/S] 2009/10 MWh/ROCs:981; LF:6.2% [2 turbines U/S] 20010/11 MWh/ROCs:708; LF:4.5% [2 turbines U/S] Rolling LF: |
| Lamb Hill | Nr. Edlingham | EHN UK | Mast Rejected. | EHN are part of the Acciona Group. Mast Application Rejected by then LPA. Not in ‘area of least constraint’. |
||||
| Longhirst | Nr. Longhirst | 6 | 130m. | “up to 2.5MW” | 13MW | Infinis (Novera) | Withdrawn (10/10) |
Withdrawn (see letter), due to landscape & vis. assessment, ground conditions and comm’s links. Next to RES’s Butterwell/Bluberry scheme. www.noveraenergy.com |
| Low Horton Farm | Nr. Blyth (E428550 N579765) |
1 | 71m. | 0.275MW | 0.275MW | ICE Renewables for the Horton Estate | Consented (23/12/11) |
Delegated decision. NCC Planning Ref. 11/02509/RENE. |
| Lynemouth (Alcan) | Lynemouth (NZ287896) |
13 | 121.2m. | 2MW | 30MW | CRE & Scottish Power | Consented 01.09 Under construction. |
|
| Maiden Hall (‘Blue Sky’) |
Nr. Widdrington | 13 | 126.5m | 3MW | 39MW | Project (website). UK Coal and Peel Energy |
Live application | NCC planning ref. 12/00290/RENEIA. Harworth Power (UK Coal) have long been looking to build a large turbine array in the Chevington area. Now proposed as supposed precursor to a wider grant-aided regeneration project for previous opencast sites with Widdrington Regeneration Partnership. |
| MSD [Merck, Sharp & Dohme] Pharmaceuticals | Cramlington | 2 | 125m. | 2.5MW | 5MW | Operational | Consented on appeal (8/08) subject to effects on civil radar (Newcastle Airport) being ameliorated. |
|
| Middle Hill | Nr. Elsdon | 9 | 125m. | 3MW | 27MW | Air Farmers Ltd. | Pre-application | |
| Middlemoor | Nr. N. Charlton (NU150228) |
18 | 125m. | 3MW | 54MW | NPower | Conditional consent (8/8/08) |
Building conditional on equipment to ameliorate impacts on Air Defence Radars being installed. Due to begin Q2/3 2012. |
| Middleton Burn | Swinhoe Farm, Nr. Belford | 16 | 125m. | 3MW | 48MW | Air Farmers Ltd. | Pre-application | Scoping appl.to NCC. Response Group: Middleton Burn Action Group (MBAG). |
| Moorhouse Farm | Nr. Lowick | 1 | 47.1m | ?MW | 0.8MW | 3R Energy solutions for Mr & Mrs L Nielsen | Live application(16/04/12) | NCC Planning Ref. 12/00841/RENE. Delegated decision unless there are objections. |
| ‘Moorsyde’ | Felkington (NT934456) |
7 | 110m. | N/A | N/A | Your Energy (Mistral) |
Refused | Refused by LPA (27/03/08) against planners’ recomm. Appeal (May-June 2009). Appeal rejected 20/01/10 by Secretary of State following Inspector’s recommendation: Decision Letter (PDF file); Inspector’s Report (large PDF file). |
| Murton | Murton | 10 | 120m. | 2MW | 20MW | RES (not listed on website) |
Not yet progressed | |
| New Bewick | Nr. Wooperton | 1 | 77.9m. | 0.5MW | 0.5MW | George F White for Harehope Estates | Refused (06/12/11) |
Decisively refused (11:0, 1 abstention), against officer recommendation. NCC Application Ref. 11/01132/RENE. |
| New Haggerston Dovecote | Nr. Haggerston (NU036435) |
1 | 37m. | 0.03MW | 0.03MW | Maden Design for Mr Howard Marshall | Refused (18/08/11) |
Exceptional recomm. refusal by NCC planners (proximity to listed dovecote). NCC Application Ref. 11/01237/FUL. |
| New Haggerston | New Haggerston | 1 | 34.2m | 0.05MW | 0.05MW | Maden Design & Build for Mr Sinclair Robson | Consented (02/02/12) |
NCC planning ref.11/02506/FUL. Endurance E-3120 turbine. |
| ‘North Covert’ (West Edington) |
Nr. West Edington (NZ155830) |
?8 | ?125m | ?MW | ?MW | TNEI, “representing Coriolis Energy Ltd. on behalf of Falck Renewables”. | Pre-application | |
| Old Felton Farm | Nr. Warkworth | ? | ?m | ?MW | ?MW | Empirica Investments | Pre-application | |
| Parkhead/Rayburn Lake | Nr. Netherwitton | 9 | 127m. | 1.8MW | 16.2MW | RES. | Application withdrawn (31/05/11) |
NCC Application No. 09/00154/RENEIA, (28/8/09). Appealed for non-det. (though NCC were still waiting on further information) Applic. withdrawn (31/05/11). Re-application expected.. |
| Pens Close Farm | Nr. Stamfordham | 1 | 34m | 0.055MW | 0.055MW | Pre-application | NCC screening opinion (12-00110-PREAPP). |
|
| Plenmeller | Nr. Haltwhistle | 24 | 92m. | 2MW | 48MW | Harworth (UK Coal) | Pre-application Mast consented (01/07) |
Northumberland County Council. Not in ‘area of least constraint’. |
| Ray Estate 1 | Nr. Kirkwhelpington | 16 | 125m. | 3MW | 48MW | Vattenfall | Consented (11/11/10). |
Joint public inquiry (with Ray & Steadings) 2008, Inspector recommended refusal on radar problems and likelihood of reaching a solution during period of consent. SoS disagreed: “is minded to grant section 36 consent and issue a section 90 direction for the Development.” (25/03/10). Final consent by Minister, subject to ‘Grampian condition’, see decision letter (PDF download). |
| Ray Estate 2. | Harwood Forest, Nr. Kirkwhelpington | 22 | 120m. | 3MW | 66MW | Vattenfall | Pre-application | Anem. Mast approved. CREDIT - Campaign for Responsible Energy Development In Tynedale. Project originated by AMEC Wind Energy Ltd. who have now sold off their wind interests. Acquired by Swedish company Vattenfall. See website page. |
| Rimside Moor (Wandystead) | Nr. Rothbury NU092066 |
3 | 91m | For G Y McNay Trust | Rejected (7/03) |
Public Inquiry - rejected on landscape impacts. |
||
| Shoreswood Farm | Ewe Hill (E393276 N646062) |
1 | 74m | 0.8MW | 0.8MW | 3R Energy for Mr William Jackson | Live application | NCC Planning Ref. 11/02725/RENE. No height information in NCC application description: “an 800kW wind turbine”. Enercon E-48 turbine proposed. |
| Steadings (Plashetts) | Nr. Kirkwhelpington | 22 | 120m. | 2-3MW | 44-66MW | Banks Developments | Refused on appeal | Joint public inquiry (with Ray & Steadings) 2008. Refused 25/03/10 by Secretary of State. See: Inspector’s Report (large PDF file) and Decision Letter (PDF file). |
| Thockrington | Nr. Bavington | 7 | 100m. | 2MW | 14MW | Wind Prospect | ‘shelved’ (15/07/06), then revised. Status now unclear. |
Previously 14 x 100m x 2MW. Anem. Mast consented 2005, now removed. Appears that Wind Prospect may now have shelved this proposal after the Steadings refusal: “adverse impact of the [Steadings] proposal on the landscape framework of the Great Bavington Conservation Area and the setting of Saint Aidan’s Church Thockrington”. Local response group: CREDIT - Campaign for Responsible Energy Development In Tynedale. |
| Tillmouth Park Farm | Nr. Cornhill-on-Tweed | 1 | 31.5m | 0.022-0.03MW | 0.022-0.03MW | Maden Design for Mr C Binnie | Operational | Consented 8/11/10. Hannevind 22/30 turbine. Dogged by problems after being commissioned. Same design as Coldingham turbine collapsed with brake failure. Hannevind declared insolvent 21 Oct. 2011. |
| Todburn East | Nr. Longhorsley (E412718 N596225) |
8 | 125m | 3MW | 24MW | Coronation Power | Pre-application | Anem. Mast appr. 29/06/2006. |
| Todd Hill | Between Pigden and Stanton. |
4 | 101m. | 2-2.5MW | “8-10MW” | Novera | Refused (06/04/10) |
NCC Planning Ref. No. 09/00083/CCMEIA. Refused (4:3), against officer’s recomm. Novera say they will not persist with this site (‘Energy firm pulls out’, Morpeth Herald, 18/02/11). |
| Toft Hill | Nr. Grindon (NT906436) |
7 | 112m. | 2.7MW | 19MW | NPower | Refused | Refused by LPA (27/03/08) following planners’ recommendation. Appeal heard (May-June 2009). Appeal rejected 20/01/10 by Secretary of State following Inspector’s recommendation. Site owned by a member of the Astor family living in Dorset. |
| Tone Hall | W. of A68 Nr. Sweethope Lough | 6 | ?100m | 2MW | 12MW | Vattenfall | Pre-application (02/02/2007) | Originated by Nuon, local information is that it has been sold on to Vattenfall, the state-owned Swedish company. 60m anem. mast approved. Local response group: CREDIT - Campaign for Responsible Energy Development In Tynedale. |
| Tranwell Airfield | Nr. Morpeth | 4 | 126m | ?MW | ?MW | Wind Ventures | Pre-application | Response Group: Action for Rural Morpeth (ARM) |
| Viewlaw | 1.5km NW of Longhorsley | 2 | 120 | 2.5MW | 5MW | Energy4All | Pre-application | Brochure download (MS Word). Contact: Paul Phare, Development Officer - paul@energy4all.co.uk, Tlf.01546 870266. Community response Group: Wingates NOT Windfarms. |
| Wandylaw | Nr. N. Charlton | 10 | 125m. | 2-3MW | 20-30MW | Ridgewind | Consented on appeal (10/2/09) |
See: Decision letter and Inspector’s Report (PDF document). Site on Ellingham estate, owned by Lady Belinda Gadsden. |
| Wansbeck Hospital | Ashington | 1 | 33m. | 0.1MW | 0.1MW | Shut down | Vestas V20-100 turbine. Commissioned 1992, shut down 2007-2009 blade damage (delamination) repaired and same fault re-appeared. Consultants report: uneconomic to repair (see press) Costs “unavailable”. Removed Dec. 2011. |
|
| Wark Common Farm | Nr. Pressen, Cornhill-On-Tweed (NT816360 ) |
1 | 71m | 0.275MW | 0.275MW | ICE Renewables for Straker-Smith Farms | Consented (02/02/12) |
Consented in spite of poor quality officer’s report and defective cut-and-paste conditions. NCC Application Ref. 11/01751/FUL. |
| Weetwood Moor | Nr. Wooler (NU015277) |
1/2 | 50m hub ?74m |
?0.8MW | ?0.8MW | Community Renewable Energy Ltd (CORE) | Abandoned | Glendale Gateway Trust voted not to pursue the project in October 2011: issues which were seen as “insurmountable” were: “a high level of borrowing, lack of confidence in the financial projections, little confidence in the deliverability of the project and the likelihood of widespread local opposition to the turbine.” (Minutes of GGT Board Meeting,12 October 2011, item 7). |
| West Ancroft | North Ancroft | 8 | 115m | 2.25MW | “approx. 18MW” | E.On UK. | Application withdrawn (02/08/10). |
“After carefully reviewing plans for our proposed West Ancroft wind farm following a recent public inquiry into nearby wind farm proposals, we have decided to withdraw our current planning application for an eight turbine scheme. We are now looking at the possibility of redesigning the project as a smaller development.” [Our emphasis]. Site is contiguous with ‘Moorsyde’ site. West Ancroft Community Action (WACA). See also: Windbyte page. |
| West Moneylaws | Nr. Mindrum (NT870345) |
6 | 125m. | 3 | 18MW | Coronation Power | Abandoned | Abandoned after scoping (01/07) Grid connection Proximity Nat. Pk. |
| Whinney Hill | Nr. Netherwitton | ? | 1??m. | ?W | ??MW | Force9 | Pre-application | Mast consented 07/03. |
| Widdrington (‘Sisters WF’) | Nr. Widdrington (NZ248952) |
4 | 126m. | 2-2.5MW | 8-10MW | Arcus for Infinis (Novera) |
Consented (07/02/12) |
NCC Planning Ref. 11/02481/RENEIA. |
| Wingates | Wingates (NZ087948) |
6 | 110m | 2-2.5MW | 12-15MW | Novera | Consented (05/04/11). |
Approved 8:2, Application Ref. 09/00084/CCMEIA. Local response group: Wingates NOT Wind Farms (WNWF). |
| Wingates Moor | Nr. Wingates (NZ098932) |
3 | 121m | 2.00-2.5MW | 8-10MW | BT | Refused (22/03/12) |
Majority decision against recommendation. NCC Application ref. 11/00158/RENEIA. Split site, another 6 turbines proposed for East Wingates Local response group: Wingates NOT Wind Farms (WNWF). |
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| Sheddon Hill | Birtley | 1 | 79.6m | 0.5MW | 0.5MW | Sternwind for Mr Robert Auld | Live Application (23/09/2011) |
Application Ref. No. DC/11/01019/FUL. Enercon E48 turbine. |
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| A & P Tyne | Wagonway Road, Hebburn (NZ311656) |
1 | 80m | 2MW | 2MW | Wind Direct for A&P Tyne | Consented (07-04-09). |
Application Ref. ST/0186/08/FUL. WES turbine. |
| Eco Centre, Hebburn | Hebburn | 1 | 45.5m. | 0.225MW | 0.225MW | Groundwork, South Tyneside | Operating (8/05) | Single, small embedded turbine
The ECO Centre, Hebburn - D (R00170RQEN): 2006/7 MWh/ROCs:162 2007/8 MWh/ROCs:234; LF:11.8% 2008/9 MWh/ROCs:232; LF:11.8% 2009/10 MWh/ROCs:165; LF:8.4% 2010/11 MWh/ROCs:158 Rolling LF: |
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| Great Eppleton | Nr. Hetton-le-Hole (NZ 366 485) |
4 | 115m. | 2.MW | 8.2MW | E.ON UK | Opened 1997 Repowered 03/10. |
4 x 69.5m 2-blade turbines (1997-2004), repowered with 4 x 115m REpower MM92 turbines.
Great Eppleton Farm (R00018RQEN): 2002/3 MWh/ROCs/:4,531; LF:17.2% 2003/4 MWh/ROCs/:2,689 2004/5 MWh/ROCs/:2,587 ------Repowered---- 2009/10 MWh/ROCs:176 2010/11 MWh/ROCs:10,152 Rolling LF: Great Eppleton WF (R00234RQEN): 2009/10 MWh/ROCs:406 2010/11 MWh/ROCs:10,837 Rolling LF: |
| Hetton Lyons Country Park | Nr. Hetton le Hole (E436313 N547528 or E436281 N547972) |
1 | 125m | 2.5MW | 2.5MW | Partnership for Renewables with Sunderland City Co. | Pre-application | |
| Nissan | Sunderland | 8 | 51m. | 0.66MW | MW | Nissan | Operating (11/05) | Small embedded turbines
SH Vestas V47. 2 more turbines consented in 2007. Turbine fire December, 2005. Nissan WF - A,C,D (R00160RQEN): 2006/7 MWh/ROCs:7,017; LF:20.2% 2007/8 MWh/ROCs:7,345; LF:21.1% 2008/9 MWh/ROCs:9,125; LF:19.2% 2009/10 MWh/ROCs:9,216; LF:16.2% 2010/11 MWh/ROCs:6,195 Rolling LF: |
| Tunstall Hills | Nr. Sunderland | 1 | 125m | 2.5MW | 2.5MW | Partnership for Renewables with Sunderland City Co. | Pre-application |
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| ‘A1’ See ‘Isles’ |
“Between Newton Aycliffe and Bradbury” | 10 | 121m. | 2-2.5MW | 20-25MW | E.ON UK | Replaced by Isles appl. | Application replaced by much larger Section 36 application for 25-45 turbines in the same area. A1 Application documents. |
| Barningham High Moor | Nr. Barningham | 25 | 54m. | 15MW | National Wind Power | Refused | Refused locally and at appeal 1998. National Wind Power (NWP) failed in its attempt to persuade the High Court to overturn The Secretary of State's
decision to refuse the grant of planning permission, 1999.
|
|
| Broom Hill | Nr. Tow Law (NZ 159392) |
4 | 102m. | 2MW | 8MW | EDF | Operational (05/2009) |
REpower MM82 turbines. Caused TV reception problems, see Press.
Broom Hill WF (R00216RQEN): 2009/10 MWh/ROCs:18,318; LF:26.1% 20010/11 MWh/ROCs:17,771; LF:25.4% Rolling LF: |
| Butterwick Moor | Nr. Sedgefield | 10 | 110m. | 2-2.5MW | 20-25MW | E.ON.UK | Operational | Immediately adjacent to Walkway scheme. German REpower MM82 turbines. Operational end of 2010. |
| ‘Crake Scar’ | Nr. Woodland | 4 | 115m. | 2MW | 8MW | Arcus for Bolsterstone Innovative Energy (Woodland) Ltd. |
Abandoned (02/12) |
Company announced abandonment on environmental grounds (local press). Banks are persisting with even worse proposal on contiguous site at Windy Bank (see below).
Response Group: Hamsterley and Upper Gaunless Action Group (HUGAG). |
| Crook Golf Club | Nr. Crook | 1 | 60.75m. | 0.5MW | 0.5MW | Green Gale Ltd for Crook Golf Club | Approved (22/03/12) |
DCC Ref. 3/2011/0178. EWT Directwind D52 turbine proposed. |
| East Close Farm | Sedgefield (NZ175373) |
1 | 84m. | 0.8MW | 0.8MW | GF White for Mr R & S Craggs | Application withdrawn (23/08/11) |
DCC Application Ref. 11/00522/FPA. Enercon E48 turbine. |
| Edder Acres | Nr. Shotton Colliery | 2 | 11.2m. | 2.3MW | 4.6MW | A7 Energy | Refused 15/11/07 |
Re-submission refused
Refused 2005 Appeal refused. |
| Fox Cover | Nr. Dawdon and Cold Hesledon, Seaham | 2 | 125m. | 3MW | 6MW | EDF Energy | Refused 01/07/08 |
Just to N. of A182. Refused by Easington DC, then LPA. |
| Foxton Lane/Shotton Beck | Heley House Farm, nr. Sedgefield | 3 | 110m. | 2MW | 6MW | Wind Prospect | Refused at appeal (03/12) |
Appealed for non-determination. Planning Appl. No. 7/2010/0236/DM. |
| The Greenhouse (Greencroft) | Nr. Consett | 1 | 43.5m. | 0.097MW | 0.097MW | Groundwork W. Durham | Operating 2006 | Small embedded.
The Greenhouse (R00161RQEN): 2006/7 MWh/ROCs/:335; LF:39.4%[?] 2007/8 MWh/ROCs/:216; LF:25.4% 2008/9 MWh/ROCs/:225; LF:26.5% 2009/10 MWh/ROCs/:224; LF:26.4% 2010/11 MWh/ROCs/:180; LF:21.2% Rolling LF: |
| Greencroft Estate | Annfield Plain, Nr. Stanley | 2 | 86.5m. | 0.8MW | 1.6MW | Lanchester Properties Ltd. | Approved (01/11/11) |
DCC Application Ref. CMA/1/51. Enercon E53 turbines proposed. |
| GSK | Barnard Castle | 2 | 45m. | 0.25MW | 0.5MW | Glaxo Smith Kline | Operating | Small embedded scheme
SH Micon turbines. Barnard Castle GSK WTs - D (R00137RQEN): 2004/5 MWh/ROCs/:415 2005/6 MWh/ROCs/:312; LF:7.1% 2006/7 MWh/ROCs/:475; LF:10.8% 2007/8 MWh/ROCs/:453; LF:10.3% 2008/9 MWh/ROCs/:289 2009/10 MWh/ROCs/:304; LF:6.9% 2010/11 MWh/ROCs/:260; LF:5.9% Rolling LF: |
| Hallfield Farm | Nr. Easington (NZ405444) |
1 | 77.9m. | 0.5MW | 0.5MW | GF White for Mr James Weightman | Approved (09/12/11) |
Planning Appl. No. PL/5/2011/0305 Directwind GA HH50 turbine. |
| Hare Hill | Nr. Peterlee (NZ 371 414) |
2 | 100m. | 2.325 & 2.75MW | 5MW | E.ON UK | Operating (2004) | NEG Micon NM80 turbines.
Hare Hill (3H) (R00140RQEN) 2.325MW: 2004/5 MWh/ROCs:2,542 2005/6 MWh/ROCs:4,683; LF:19.4% 2006/7 MWh/ROCs:4,162 2007/8 MWh/ROCs:5,146 2008/9 MWh/ROCs:4,838 2009/10 MWh/ROCs:5,608; LF:23.3% 20010/11 MWh/ROCs:7,714; LF:32.0%[?] Rolling LF: Hare Hill WF (E.On) - A, C (3H) (R00139RQEN) 2.75MW: 2004/5 MWh/ROCs:2,240 2005/6 MWh/ROCs:4,520; LF:18.8% 2006/7 MWh/ROCs:4,525 2007/8 MWh/ROCs:4,147 2008/9 MWh/ROCs:4,503; LF:18.7% 2009/10 MWh/ROCs:4,780; LF:19.8% 20010/11 MWh/ROCs:4,076 Rolling LF: |
| Haswell Moor | Nr. Haswell/Sherburn | 5 | 110m. | 2.05MW | 10.25MW | E.ON.UK | Operating (12/10). | German REpower MM82 turbines. |
| Hawthorn | West of A19, nr. Murton (NZ405460/NZ408463). | 2 | 105m. | 2.5MW | 5MW | SLP Energy | Refused (16/03/10) |
Initial application April 2008, withdrawn September 2008. Resubmitted (Non-technical summary available). |
| High Haswell | Nr. Haswell | 2 | 100m. | 2MW | 4MW | Consent sold to REG | Operational | Renewable Energy Generation (REG), acquired High Haswell for £800,000 in January 2010. Two Vestas V80 turbines acquired, commissioned March, 2011. |
| High Hedley Hope | Nr. Tow Law (NZ142405) |
3 | 71m. | 0.75MW | 2.25MW | EDF/London Power Co. | Operating (2002) | Hedley Hope (R00032RQEN): 2002/3 MWh/ROCs:5,087; LF:25.8% 2003/4 MWh/ROCs:5,841; LF:29.6% 2004/5 MWh/ROCs:6,620; LF:33.6% 2005/6 MWh/ROCs:5,998; LF:30.4% 2006/7 MWh/ROCs:6,136; LF:31.1% 2007/8 MWh/ROCs:6,040; LF:30.6% 2008/9 MWh/ROCs:5,037; LF:25.6% 2009/10 MWh/ROCs:4,351; LF:22.1% 20010/11 MWh/ROCs:4,548; LF:23.1% Rolling LF: |
| High Hedley Hope 2 | Nr. Tow Law | 4 | 105m. | 1.3MW | 5.2MW | EDF/London Power Co. | Operating (10/08) |
Nordex N60 turbines. High Hedley 2 (R00209RQEN): 2008/9 MWh/ROCs:9,185 2009/10 MWh/ROCs:9,650; LF:21.2% 20010/11 MWh/ROCs:9,225; LF:20.3% Rolling LF: |
| High Sharpley | Nr. Seaham. | 2 | 90m. | 1.3MW | 2.6MW | Cornwall Light & Power Company Ltd./REG | Operating (2007) | See also extension at South Sharpley.
Nordex N60 turbines High Sharpley - A (R00177RQEN): 2006/7 MWh/ROCs:1,403 2007/8 MWh/ROCs:6,479; LF:28.4%% 2008/9 MWh/ROCs:5,797; LF:25.5% 2009/10 MWh/ROCs:5,537; LF:24.3% 20010/11 MWh/ROCs:4,416; LF:19.4% Rolling LF: |
| High Stoop | Nr. Tow Law (E410744 N539635) |
1 | 66.7m | 0.33MW | 0.33MW | Empirica Investments | Pre-application | |
| High Volts | Elwick, Hartlepool (NZ452333) |
3 | 100m. | 2.75MW | 8.1MW | Powergen | Operating (12/03) | NEG Micon NM80 turbines.
High Volts WF (3H), R00133RQEN (1T, 2.325MW): 2003/4 MWh/ROCs:2,609 2004/5 MWh/ROCs:3,833 2005/6 MWh/ROCs:4,099 ---TIGC: 1.156MW--- 2006/7 MWh/ROCs:2,707 2007/8 MWh/ROCs:5,313 ; LF:22.0% 2008/9 MWh/ROCs:5,106; LF:21.2% 2009/10 MWh/ROCs:3,987 20010/11 MWh/ROCs:5,085; LF:21.1% Rolling LF: High Volts Wind Farm 2 (3H), R00132RQEN (2T, 5.5MW): 2003/4 MWh/ROCs:1,121 2004/5 MWh/ROCs:7,258 2005/6 MWh/ROCs:10,736; LF:22.3% 2006/7 MWh/ROCs:7,835 2007/8 MWh/ROCs:10,118; LF:20.9% 2008/9 MWh/ROCs:7,520; LF:15.6% 2009/10 MWh/ROCs:9,442; LF:19.6% 20010/11 MWh/ROCs:6,831 Rolling LF: |
| High West Moor Farm | Nr. Tow Law | 1 | 66.7m | 0.33MW | 0.33MW | Empirica Investments | Pre-application | |
| Holmside | Nr. Stanley (NZ208493) |
2 | 100m. | 2.75MW | 5.5MW | E.ON UK | Operating (2004) | NEG Micon NM80 turbines.
Holmside WF - A,C (3H), R00141RQEN (1T, 2.75MW): 22004/5 MWh/ROCs:2,626 2005/6 MWh/ROCs:5,600; LF:23.2% 2006/7 MWh/ROCs:2,937 2007/8 MWh/ROCs:4,152 ; LF:17.2% 2008/9 MWh/ROCs:3,869 2009/10 MWh/ROCs:5,142; LF:21.3% 20010/11 MWh/ROCs:4,408 Rolling LF: Holmside Hall (3H), R00142RQEN (1T, 2.325MW): 22004/5 MWh/ROCs:3,167 2005/6 MWh/ROCs:4,215; LF:17.5% ---TIGC: 1.119MW--- 2006/7 MWh/ROCs:4,682 2007/8 MWh/ROCs:4,432 2008/9 MWh/ROCs:4,945; LF:20.5% 2009/10 MWh/ROCs:4,594; LF:19.1% 20010/11 MWh/ROCs:4,924; LF:20.4% Rolling LF: |
| INEOS Newton Aycliffe Ltd. (Formerly Hydro Polymers). |
Newton Aycliffe | 2 | 48m. | 0.25MW | 0.5MW | Hydro Polymers/TNEI | “Project cancelled” (2008) |
Small embedded scheme Plastics plant. |
| ‘Isles’ (‘A1’ revision) |
“East of Newton Aycliffe” | 25-45 | 121m | 2.5MW | 115MW | E.ON UK | Pre-application | Section 36 application for 25-45 turbines in the same area as the “dormant” A1 application (above). Community response group: Isles Communities Turbine Action Campaign |
| Junction House | Nr. Easington | 1 | 99.5m | 2.3MW | 2.3MW | BT | Appeal Refused (19/03/12) |
Appeal Ref: APP/X1355/A/11/2164485 (decision letter). Appl. Ref. No. PL/5/2010/0473 Refused on 11:1 vote. |
| Langley | Nr. Burnhope (NZ200 474) |
4 | 102m. | 2MW | 8MW | EDF | Operating | REpower MM82 turbines. Consented 6/05. Commissioned 13/08/2008. Caused problems with TV reception (see website). Langley, R00212RQEN (4T, 8.0MW): 2008/9 MWh/ROCs:11,026 2009/10 MWh/ROCs:17,713; LF:25.3% 20010/11 MWh/ROCs:16,077; LF:22.9% Rolling LF: |
| Low Raisby Farm | Nr. Kelloe | 1 | 76m | 0.5MW | 0.5MW | AMEC for Mr J Taylor | Withdrawn (27/02/2012) |
Appl. Ref. 11/00923/FPA.EWT DW52 turbine proposed. |
| Murton Moor | Nr. Murton (E437838 N546478) |
1 | 74m | ?MW | MW | Savills for Mr Martyn Dryden | Pre-application | Application for 40.5m Anem. mast, PL/5/2012/0009 (16/01/2012) |
| Oakenshaw | Nr. Oakenshaw | 3 | 1??m. | 2.75MW | 8.25MW | EDF Energy | Pre-application | |
| Ponder Gill | Nr. Barnard Castle | 5 | 45m. | ?MW | ?5MW | Pre-application | Next to the A66, at Cross Lanes. |
|
| Quarrington Hill | Nr. Cassop | 2 | 3MW | 6MW | Eco energy | Refused (2004) | Appeal rejected |
|
| Sheraton Hill | Nr. Peterlee (E444600 N536867) |
5 | 115m | 2MW | 10MW | EDF | Live application (23/01/12 ) |
Application Ref. CMA/5/31 1 turbine in Hartlepool. |
| Shotton Farm | Nr. Sedgefield | 1 | 66.5m | 0.33MW | 0.33MW | GF White for Landowner | Pre-application | Screening opinion sought, 01/11. 0.5km from Foxton Lane (Live appl.), also close to Lamb's Hill (consented). Enercon E33 turbine proposed. |
| South Sharpley | Nr. Seaham, Co Durham | 3 | 100m. | 2.5MW | 7.5MW | Cornwall Light & Power Company Ltd./REG | Consented at appeal (07/04/11 |
Extension to existing scheme at High Sharpley. Unanimous refusal following officer’s recommendation. Major reason: proximity to housing (450m). Overruled on everything by one of the Inspectorate’s wind warriors (App. Ref. APP/X1355/A/10/2127599). |
| Stanley Moss | Nr. | 2 | 107m. | 2.3MW | 4.6MW | Amec/Banks Group | Refused (6/04) |
|
| Stobhill | Nr. Bolam | 7 | Up to 125m. | 2-2.5 MW | 14-17.5MW | NPower | Dropped | RWE NPower have announced that “RWE npower renewables has made a decision not to proceed further with an application for a wind farm near Bishop Auckland at the present time. [...] information from the Ministry of Defence (MoD) concerning a radar at nearby RAF Leeming has meant that RWE npower renewables feel it would not be sensible to progress the scheme further at present.”
|
| Tanners Hall Farm | Oakenshaw, Nr. Crook (NZ175373) |
1 | 64m. | 0.25MW | 0.25MW | VG Energy for Mr A Layfield | Application withdrawn (23/08/11) |
DCC Application Ref. 11/00522/FPA. Vestas V52 turbine. |
| Thornley Pit House Farm | Nr. Tow Law (E412888 N538686) |
1 | 34.2m | 0.05MW | 0.05MW | JDA Architects for Mr Suddes | Refused (17/04/12) |
DCC Application Ref. CMA/3/37. Endurance E-3120 turbine proposed. |
| Tow Law | Nr. Tow Law (NZ140406 ) |
3 | 71m. | 0.77MW | 2.31MW | National Wind Power | Operating | Nordex N50 turbines, commissioned 01/12/2001.
Tow Law Wind Farm, R00033RQEN (3T, 2.31MW): 2002/3 MWh/ROCs:4,950; LF:24.5% 2003/4 MWh/ROCs:5,852; LF:28.8% 2004/5 MWh/ROCs:6,280; LF:31.0% 2005/6 MWh/ROCs:5,819; LF:28.8% 2006/7 MWh/ROCs:6,229; LF:30.8% 2007/8 MWh/ROCs:2,988; LF:14.7% 2008/9 MWh/ROCs:5,271; LF:26.0% 2009/10 MWh/ROCs:4,809 ; LF:23.8% 2010/11 MWh/ROCs:4,601; LF:22.7% Rolling LF:25.9 % |
| Trimdon Grange | Nr. Trimdon | 4 | 76m. | 1.3MW | 5.2MW | EDF | Operating (10/07/2008) |
Nordex N60 turbines. Consented on appeal, 2005. Trimdon Grange, R00210RQEN (4T, 5.2MW): 2008/9 MWh/ROCs:6,479 2009/10 MWh/ROCs:8,367; LF:18.4% 2010/11 MWh/ROCs:7,587; LF:16.7% Rolling LF:18.0% |
| Trimdon House Farm & West House Farm | Nr. Ferryhill (E435045 N533476) |
2 | 77m. | 0.5MW | 1MW | Myriad CEG for Mr G Hirst & D Morgan | Live application (05/08/11) |
Planning Appl. No. 7/2011/0293/DM . |
| Twizell Hall Farm | Nr. Stanley (E421880 N551934) |
2 | 39.6m | 0.05MW | 0.1MW | ML Planning for Mr Dan Harrison | Application withdrawn (17/02/12) |
Planning Appl. No. 2/11/00336/FUL. CF50 wind turbine proposed. |
| Walkway | Nr. Sedgefield (NZ401302) |
7 | 110m. | 2 | 14MW | Wind Prospect | Operating (04/2008) |
REpower MM82 turbines.
Immediately adjacent to Butterwick scheme. Operating as 2 entities (Walkway 1 [R.O. ID R00197RQEN], 4 turbines & Walkway 2 [R.O. ID R00198RQEN], 3 turbines) Walkway WF 1, R00197RQEN (4T, 8.0MW): 2008/9 MWh/ROCs:10,984; LF:15.7% 2009/10 MWh/ROCs:13,795; LF:19.7% 2010/11 MWh/ROCs:13,212; LF:18.9% Rolling LF:19.3 % Walkway WF 2, R00198RQEN (3T, 6.0MW): 2008/9 MWh/ROCs:13,587; LF:25.9% 2009/10 MWh/ROCs:13,102; LF:24.9% 2010/11 MWh/ROCs:10,636; LF:20.2% Rolling LF:24.9% |
| ‘West Durham’ | Nr. Satley/Tow Law (NZ115414) |
12 | 100m. | 2MW | 24MW | Banks Developments Now ESB. |
Operating (5/09) |
REpower MM82 turbines. Acquired by Irish energy firm ESB (Irish Government-owned Electrical Supply Board). Breakdown 18/05/11- West Durham WF, R00219RQEN (12, 23.9MW): 2009/10 ROC's/MWh:54,157; LF:25.8% 2010/11 ROC's/MWh:58,017; LF:27.6% Rolling LF:27.1 % |
| West Shipley | Nr. Hamsterley | ? | ?m. | ?MW | ?MW | Pure Renewable Energy | Pre-application | 50m Anemometer mast approved 24/05/11 (2 years), ref. 6/2011/0110/DM
Response Group: Hamsterley and Upper Gaunless Action Group (HUGAG). |
| ‘Windy Bank’ | Nr. Woodland | 5 | 115m. | 2.5MW | 12.5MW | Banks Developments | Live Application (08/08/11) |
DCC Planning Ref. CMA/6/48.
Contiguous with Crake Scar (see above). Community Response Group: Hamsterley and Upper Gaunless Action Group (HUGAG). |
| Wingate Grange | Nr. Peterlee (NZ385379) |
5 | 115m. | 2-2.5MW | 10-12.5MW | Infinis | Pre-application | 60m Anem. mast approved 13/07/11, ref. PL/5/2011/0196.
|
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| Red Gap Farm | Wolviston, Hartlepool | 5 | 125m. | 3MW | 15MW | BT | Approved (3/2/2010). |
Ref. H/2009/0231. |
| Sheraton Hill | Nr. Peterlee (E444600 N536867) |
1 (5) | 115m | 2MW | 10MW | EDF | Live application (23/01/12 ) |
Application Ref. CMA/5/31 1 turbine in Hartlepool. |
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| Middlesbrough Football Club | Land adjacent to Riverside Stadium | 1 | 125m | 3MW | 3MW | Middlesbrough FC | Approved (07/07/08) |
Application Ref. M/FP/0849/08/P. |
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| ASDA Teesport | Middlesbrough (NZ560237) |
1 | 100m | 0.850-1.0MW | 0.85-1.0MW | Green Peninsula for ASDA | Live application (15/12/2009) |
Planning Application Ref. R/2009/0832/FF. |
| Barnaby Side Farm | Nr. Middlesbrough (NZ569167) |
1 | 53.5m | 0.33MW | 0.33MW | GF White for Mr John Rider | Live application | Planning Application Ref. R/2011/0098/SC. Enercon E33 turbine proposed. |
| Beacon Moor | Nr. New Marske (NZ625198) |
4 | 115m. | 2.5MW | 10MW | Infinis | Abandoned (03/12) | Application for 60m anem. mast approved (Ref. R/2011/0374). |
| Marske Estate | Nr. Saltburn (NZ663152) |
4 | 100m | 0.8MW | 3.2MW | Knight Frank LLP for West Midlands Metropolitan Authority Pension Fund | Pre application | Screening request R2011/0665/SC Sept. 2011; Scoping report Dec. 2011. Enercon E48 turbines proposed. |
| Ridge Farm | Nr. Stanghow (NZ663152) |
1 | 67m | 0.33MW | 0.33MW | Empirica Investments | Live application (04/01/12) |
Appl. Ref. R/2012/0005/FF. Enercon E33 turbine proposed. |
| Teesside Offshore | 1.5km (!) off Coatham Sands, Redcar | 27 | 152m. | 2.3MW | 62MW | Northern Offshore Wind/EDF | Under construction | Consented 17/09/07, Sect. 36 decision. Siemens 2.3MW turbines ordered. |
| Teeswind North | Corus steel site, Redcar | 18 | 140m. | 2.5MW | 45MW | AMEC/Corus | Consented (16.07.02 - R/2001/936/FF) "In abeyance" |
|
| Tees Wind South | Corus steel site, Redcar (NZ545220) |
10 | 140m. | 2.5MW | 25MW | AMEC/Corus | "In abeyance" | |
| Upsall Grange | Nr. Nunthorpe (NZ549161) |
1 | 47.1m | 0.1MW | 0.1MW | GF White for Landowner | Pre-application | Screening opinion sought, 06/11. Northwind 100kW turbine proposed. |
| West Field Farm | Nr. Loftus | 1 | 66.6m | 0.33MW | 0.33MW | Savills for Landowner | Pre-application | Screening opinion sought, 08/11. Enercon E33 turbine proposed. |
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| Augean Landfill Site | Port Clarence, Nr. Billingham. | 4 | 126m. | ? | ? | Augean PLC | Pre-application | Scoping opinion sought N/2009/0006/SO. |
| Bishopsgarth School | Bishopsgarth, Stockton-on-Tees | 1 | 47.5m | N/A | N/A | TNEI for school | Operating | Approved 08/08/06. |
| HBC Vehicle Breakers | Nr. Billingham. | 1 | 125m. | 2.5MW | 2.5MW | Infinergy | Pre-application | Scoping opinion sought 2006. |
| Seamer | Between Hilton and Seamer, nr. Yarm, on Stockton-on-Tees and N. Yorks boundary. | 5 | 125m. | “Up to 3MW” | “Up to 15MW” | Broadview Energy | Consented | Refused against recomm. by SBC (3 turbines); 11/08) and HDC, Yorkshire (2 turbines; 10/08). Revised appl. approved on Chair’s vote by SBC ; HDC refused by 7:5 (17/9/09); subsequently approved at appeal. |
| Stillington/Lamb’s Hill | Stillington, Nr Stockton (NZ358238) |
4 | 125m. | 2-2.5MW | 8-10MW | Banks Developments/Gaz de France | Consent quashed 09/11 |
Consent (02/03/2011) quashed on procedural grounds (see article). Resubmission expected imminently. original Application ref. No. 10/2549/EIS Banks are also considering developing a 4MW combined heat and power (CHP) facility on Stillington Industrial Estate. |
| Vertellus | Seal Sands, Middlesbrough | 1 | 150m | 2.5MW | 2.5MW | Wind Direct for Vertellus | Pre-application | Scoping request ref. 11/3173/SOR, (19/12/11). 800m from Teesmouth National Nature Reserve, SSSI etc. |
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| Coniscliffe Grange Farm | Nr. Darlington (E425548 N515596) |
1 | 34.4m | 0.055MW | 0.055MW | GF White for Manners Farms | Consented (28/03/12) |
Appl. Ref. 12/00021/FUL. Endurance turbine proposed. |
| East/West Newbiggin | Nr. Sadberge, Darlington. | 3 | 110m. | ?MW | ?MW | Pure Renewable Energies, PB Power. | Live application(29/03/11) | DBC Case Ref. 11/00128/FUL |
| Moor House | Nr. Barmpton, Darlington. | 6 | 125m | 2.5MW | 15MW | Banks Developments | Consented (18/10/11) |
Banks put in a parallel proposal for 6 turbines in March 2011 after a 10T application was refused (10/11/10) then appealed (June 2011). LPA rec. approval despite project exceeding rec. capacity (4-6 turbines) and objections from local airport. Community response Group: SPAG -Seven Parishes Action Group (contact: Peter Wood, 0844 209 1515). |
| Royal Oak | Nr. Shildon (NZ208238) |
5 | 105m. | 1.3MW | 6.5MW | EDF/Harworth Power (UK Coal). | Consented (10/05) | “Construction on the site is due to commence in the near future once tendering has been completed for the project.” |
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| Ballencrieff Farm | Nr. Bathgate (NS983708) |
1 | 67m | 0.5MW | 0.5MW | WRS Energy for landowner | Withdrawn (18/07/11) |
Appl. Ref. 0386/FUL/11. EWT Direct wind 750 turbine proposed. |
| Bankhead Farm | Nr. Detchmont (NT029726) |
1 | 48m | 0.1MW | 0.1MW | 3R Energy solutions for landowner | Withdrawn (14/07/11) |
Appl. Ref. 0373/FUL/11. |
| Black Law | Nr. Forth | 8 (54) | 110m | 2.3MW | 18.5MW (124MW) | Sc. Power (Iberdrola) | Operational (2006) |
Most of the turbines are in Lanarkshire.
Black Law WF - A,C, R00060SQSC (54, 124.2MW):
2004/5 MWh/ROCs:1,914 2005/6 MWh/ROCs:168,471; LF:19.9% 2006/7 MWh/ROCs:269,294 ; LF:24.8% 2007/8 MWh/ROCs:263,370; LF:24.1% 2008/9 MWh/ROCs:249,740; LF:23.0% 2009/10 MWh/ROCs:208,834; LF:19.2% 2010/11 MWh/ROCs:194,406; LF:17.9% Rolling LF:22.1% |
| Black Law Ext., Phase I | Nr. Forth (NS918570) |
8 (23) | 126.5m | 3MW | 24MW (69MW) | Sc. Power (Iberdrola) | Live application (2008) |
Section 36 application. Most of the turbines are in Lanarkshire. Another 12 turbines (BL Phase II, Scoping doc. pdf)) are proposed within the N Lanarks. boundary, access corridor within West Lothian. |
| Burnhead Farm | Nr. Limerigg (NS 88335 69285) |
? | ?m. | ?MW | ?MW | Wind Prospect | Scoping | 70m anemometer mast. Planning ref. 0234/EXC/10 |
| Fauch Hill | Nr. West Calder | 23 | 125m. | 3MW | 69MW | Fauch Hill Sustainable Energy | Scoping | Section 36 application to Scottish Govt. Scoping opinion available on ECU website. Project and land owned owned by European Forest Resources, owned by French energy conglomerate the Louis Dreyfus Group. Community Response Group: North Pentlands Windfarm Action Group (NPWAG). |
| Gowanbank Farm | Nr. Avonbridge (NS913715) |
1 | 67m | 0.5MW | 0.5MW | WRS Energy for landowner | Withdrawn (18/07/11) |
Appl. Ref. 0387/FUL/11. EWT Direct wind 750 turbine proposed. |
| Harburnhead | Nr. West Calder | 22 | 125m. | 2.3MW | 50.6MW | Luz de Viento (LDV) | Live Application (01/12) |
Section 36 application to Scottish Govt. Public consultation ended 10/02/12 (over 500 objections lodged). Community Response Group: North Pentlands Windfarm Action Group (NPWAG). |
| Heights Farm | Nr. Blackridge (NS898688) |
1 | 67m | 0.5MW | 0.5MW | WRS Energy for landowner | Withdrawn (15/07/11) |
Appl. Ref. 0389/FUL/11. EWT Direct wind 750 turbine proposed. |
| Kipps Farm | Nr. Linlithgow (NS 98941 73570) |
1 | 34.2m | 0.05MW | 0.05MW | Scaled Energy for landowner | Refused (16/11/11) |
Appl. Ref. 0510/FUL/11 Endurance E3120 turbine proposed. |
| Latch Farm | Nr. Kirknewton (NT092651) |
1 | 77m | 0.5MW | 0.5MW | Arcus for Intelligent Land Investments | Withdrawn (21/06/11) |
Appl. Ref. 0266/FUL/11. |
| Pates Hill | Nr. West Calder | 7 | 107m. | 2MW | 14MW | Your Energy | Operational (02/10). |
Vestas V-80 turbines.
Consented June 2007. Project bought from ‘New Lives New Landscapes’. Pates Hill WF, R00127SQSC (7, 14MW): 2009/10 MWh/ROCs:3,916 2010/11 MWh/ROCs:26,488; LF:21.6% Rolling LF:21.3 % |
| Pates Hill II | Nr. West Calder | ? | 1??m. | ?MW | ??MW | Your Energy | Scoping | Community Response Group: North Pentlands Windfarm Action Group (NPWAG). |
| Pearie Law | Nr. West Calder | 6 | 125m. | 2MW | 12MW | EDF | Live application (17/04/12) |
WLC Planning Ref. 0267/FUL/12. Community Response Group: North Pentlands Windfarm Action Group (NPWAG). |
| Tormeywheel | Fauldhouse (NS951581) |
15 | 102m. | 2.75MW | 41.25MW | Your Energy/PI Renewables | Conditional Consent (08/06/07) |
Consented at appeal, June 2007 (appeal decision) despite effects on Edinburgh Airport radar. Section 42 appl. to extend life of the planning permission to June 2014 approved (Ref. No. 0551/FUL/11). |
| West Craigmarrie Farm | Nr. Armadale (NS915697) |
1 | 67m | 0.5MW | 0.5MW | WRS Energy for landowner | Withdrawn (15/07/11) |
Appl. Ref. 0390/FUL/11. EWT Direct wind 750 turbine proposed. |
| Woodend Farm | Nr. Armadale (NS910695) |
1 | 67m | 0.5MW | 0.5MW | WRS Energy for landowner | Withdrawn (15/07/11) |
Appl. Ref. 0388/FUL/11. EWT Direct wind 750 turbine proposed. |
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| Auchencorth Moss | Nr. Penicuik (NT210567) |
14 | 102m. | 2.5MW | 35MW | E.On UK | Appeal rejected (11/06/2010) |
Refused by LPA 11:3 following Officer’s rec. Appeal Dismissed (11/06/2010) - decision letter (PDF file). Response Group: PEPA |
| Bowbeat extension | Nr. Peebles | 1 (5) | 110m | 2.3MW | 9.2MW | E.ON UK | Scoping (2008) | 4 turbines in Midlothian, 1 in Scottish Borders.
|
| Cousland Equestrian Centre | Nr. Inveresk (NT376688) |
1 | 45.7m | 0.225MW | 0.225MW | Passim Developments for Mr Ian Ross | Live Application (17/06/11) |
Planning Ref. 11/00402/DPP
ACSA-A27 turbine proposed. |
| Fordel Inn | Fordel, Dalkeith (NT360668) |
1 | 47.5m | 0.1MW | 0.1MW | SAC Commercial for R H Miller (Agric.) | Application refused (18/01/11) |
Planning Ref. 10/00163/DPP
|
| Mount Lothian | Nr. Penecuik | 12 | 105m | ?MW | ?MW | Wind Prospect | Pre-application | Part of Penecuik Estate.
|
| Southfield Farm | Nr. Cousland (E338146 N667574) |
1 | 34.2 m | 0.05MW | 0.05MW | Realise Renewables for Mr David Dalrymple | Consented (26/04/12) |
Planning Ref. 12/00051/DPP.
Endurance E-3120 turbine proposed. |
| Whitebog Stables | Nr. Rosewell (NT296633) |
1 | 45.7m | 0.225MW | 0.225MW | Passim Developments for Doreen Monteith | Application withdrawn (08/11/11) |
Planning Ref. 11/00502/DPP
ACSA-A27 turbine proposed. |
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| Abbey Mains | Nr. Haddington (NT535759) |
1 | 34.2m. | 0.05MW | 0.05MW | Passim Developments for J K Playfair & Sons | Live application (19/04/12) |
|
| Aikengall | Nr. Innerwick (NT694694) |
16 | 125m. | 3MW | 48MW | Community Windpower Ltd. | Operational (5/09). |
Vestas V90 turbines.
Consented 13/03/07, against Officer's advice by Convenor’s casting vote. Site in AGLV, SSSI within site. Contiguous with Crystal Rig. Unlike CR, is very visible from the coast. Aikengall WF, R00095SQSC (16T, 48MW): 2008/9 MWh/ROCs:32,124 2009/10 MWh/ROCs:148,643; LF:35.4% 2010/11 MWh/ROCs:126,147; LF:30.0% Rolling LF:32.6 % |
| Aikengall II/Wester Dod | Monynut Edge, Nr. Innerwick (NT712676) |
22 | 125m | ?3MW | ?66MW | Community Windpower Ltd. | Live Application Rev. 07/10. PI held. |
30 turbines until July 2010: 22 in East Lothian, 8 in SBC area (objection from SBC). Section 36 application, see: Scottish Consents website. Response group: Save the Lammermuirs (STL). |
| Alderston Mains | Huntington, nr. Haddington | 1 | 34.2m. | 0.05MW | 0.05MW | The Green Company Mr G Hastie |
Consented (24/09/10) |
|
| Amisfield Farm | Nr. Haddington (351495 675732 or 352035 675314) |
1 | 67m. | 0.33MW | 0.33MW | 3R Energy Solutions for landowner | Screening (24/03/10) |
|
| Belhaven Fruit Farm | Nr. Dunbar (677580 3650314) |
2 | 37.5m | 0.03MW | 0.06MW | Maden Design for Mr Ian Rennie | Live application (22/10/10) |
2 Hannevind 22/30kw turbines (Hannevind declared insolvent 21 Oct. 2011). Application Ref. 10/00911/P. Local response group: SABEL. |
| Baro Farm | Nr. Garvald (355665 669438) |
2 | 47.5m | 0.1MW | 0.2MW | Myriad CEG for landowner | Live application | |
| Belhaven Trout Co. | Nr. Dunbar (677590 364686) |
2 | 37.5m | 0.03MW | 0.06MW | Maden Design for Mr Ian Rennie | Live application (22/10/10) |
2 Hannevind 22/30kw turbines (Hannevind declared insolvent 21 Oct. 2011). Application Ref. 10/00910/P. Local response group: SABEL. |
| Brownrigg Farm | Nr. North Berwick | 1 | 37.5m. | 0.03MW | 0.03MW | Maden Design for Mr John Trainer | Refused (19/08/11) |
1 Hannevind 22/30kw turbines (Hannevind declared insolvent 21 Oct. 2011). Application Ref. 10/00913/P. Local response group: SABEL. |
| Cairndinnis Farm | Traprain, East Linton (674683 357062) |
2 | 37.5m. | 0.03MW | 0.06MW | Maden Design for Mr Euan Smith | Live application (01/04/11) |
|
| Carfrae Farmhouse | Gifford, nr. Haddington | 1 | 34.2m | 0.05MW | 0.05MW | 3R Energy Solutions Mr H Gibson |
Refused (21/10/11) |
|
| Cockielaw | Nr. Haddington E359126 N673400 |
1 | 40.4m | 0.1MW | 0.1MW | 3R Energy Solutions Mr James Clerk (dec'd.) |
Refusal appealed (20/03/12) |
Appeal Ref. 12/00001/P01. Refused at review after delegated refusal - landscape impacts on Traprain Law. . Application Ref. 11/00042/P. Local response group: SABEL. |
| Colstoun House | Nr. Haddington (352877 670241) |
1 | 51m | 0.5MW | 0.5MW | Intelligent Land Investments (Renewable Energy) Ltd | Withdrawn (20/02/12) |
|
| Crossgatehall (Standingstone) | Nr. Haddington N673373 E356700 |
1 | 67m | 0.33MW | 0.33MW | 3R Energy Solutions for Mr James Clark | Application withdrawn (28/02/12) |
|
| Crystal Rig, Phase 2. | (NT660690) | 29 (52) | 30x110m 22x125m. |
128.8MW | Natural Power | Operating (09/09/2010) |
Consented (01/05/04), 23 Turbines in Sc. Borders
29 in East Lothian. Site in AGLV. Crystal Rig II WF, R00103SQSC (60T, 135.365MW): 2009/10 MWh/ROCs:14,996; 2010/11 MWh/ROCs:299,908; LF:24.8% Rolling LF:23.2% |
|
| Crystal Rig, Phase IIa | (NT678678) | 9 | 125m. | 3MW | 27MW | Natural Power | Operating (09/09/2010) |
Nos. Increase to Crystal Rig 2.
Site in AGLV, 2.3km of new access tracks. |
| Crystal Rig - ‘Phase 3’ | North of existing Phase 2 | 11 | 125m. | ?MW | ?MW | Natural Power for Fred Olsen Renewables |
Scoping | See: ‘Crystal Rig III Wind Farm, Environmental Impact Assessment Scoping Report, July 2010’ (3.8Mb PDF download). Yet another increase to the Crystal Rig complex. Very low (£1K per MW, p.a.) community fund offered. Site in AGLV. Exhibitions: Wed., 15 Feb. 2012, 4-8pm Co’path Vill. Hall Thurs., 16 Feb. 2012, 4-8pm Garvald Vill. Hall. Response group: Save the Lammermuirs (STL). |
| Dunbar [Lafarge Cement Works] | Nr. Skateraw, Dunbar | 3 | 100m. | 2MW | 6MW | EDF | Live application | |
| East Mains, Samuelston | Nr. Haddington | 1 | 48m | 0.1MW | 0.1MW | 3R for J & AJ Thomsen | Pre-application | ELC screening opinion 14/06/11. |
| New Mains, Fenton Barns | Nr. North Berwick E351155 N681019 |
3 | 30m | 0.015MW | 0.045MW | Vigor Renewables | Consented (30/07/10) |
|
| Ferneylea | Nr. Cockburnspath E374697 N669900 |
2 | 71m | 0.275MW | 0.55MW | Tods Murray LLP for Mr John McGregor |
Refused (07/03/12) |
|
| Forth Array (Offshore) |
17km off St Abbs Head | 70-90 | 163m. | 5MW | 415MW | Fred Olsen Renewables Ltd | Abandoned | FOR have announced withdrawal in favour of onshore development. (BusinessGreen, 19 Nov 2010) SBC “Scoping Opinion requested 23 March 2010 (provided 8 April 2010)”. Site covered c. 130 sq. km. |
| Harperdean Farm | Nr. Haddington E350708 N675374 |
1 | 33.05m | 0.053MW | 0.053MW | V G Energy for J & W Jenkinson | Live application (21/11/11) |
|
| Hoprig Farm | Nr. Longniddry (NT454743) |
1 | 47.5m | 0.1MW | 0.1MW | Locogen for landowner | Pre-application | |
| Howden Farm | Nr. Gifford E349622 N667958 |
1 | 34.4m | ?MW | ?MW | VG Energy for Mr Douglas Scott | Consented (05/12/11) |
|
| Keith Hill | NE of Dun Law (Soutra) adj. to Pogbie | 6 | 76m | 0.8MW | 4.8MW | Energy workshop for Mr Sandy Hodge | Consented (01/04/11) |
Planning Ref. 10/00985/P. Previous application for 10 x 93.5m turbines refused by ELC (02/09/09) on landscape grounds. Appeal refused (15/02/10) P/PPA/210/2006. |
| Kidlaw Farm | Nr. Gifford (NT509635) |
1 | c. 80m | c. 1.0MW | c. 1.0MW | Energy Workshop for landowner | Pre-application | |
| Markle Mains | Nr. East Linton N673373 E356700 |
1 | 48m | 0.1MW | 0.1MW | Smiths Gore for A W & A Middlemass | Live application (20/04/11) |
|
| Marvingston Farm | Nr. Gifford (NT508659) |
1 | 74m | 0.8MW | 0.8MW | Locogen for landowner | Live application (08/08/11) |
|
| Muirton Farm | Nr. Drem N673373 E356700 |
2 | 34.2m | 0.05MW | 0.1MW | Green Company for Mr Douglas Russell | Refused (26/08/11) |
|
| Newlands Farm | Nr. Gifford | 1 | 35m | 0.05MW | 0.05MW | Arcus for landowner | Pre-application | |
| Over Hailes | Nr. East Linton | 2 | 46m | 0.05MW | 0.1MW | The Green Co. for landowner. | Live application | |
| Pogbie | Pogbie, Nr. Soutra Law | 6 | 76m | 0.85MW (Vestas V52) |
5.1MW | Natural Power Pogbie Farms |
Consented (02/09/09) |
Planning Ref. 08/00823/FUL. East side of A68, Just north of Dun Law I/II. |
| Rowan Park | Nr. Gifford | 1 | 76m | 0.5MW | 0.5MW | Arcus/Temporis for landowner | Application withdrawn (15/11/11) |
|
| Ruchlaw Mains | Nr. Stenton | 1 | 48.7m | 0.1MW | 0.1MW | Ecodyn for Mr James Wyllie | Operating | ELC Ref. 09/00837/P. 510m from Stenton Village. |
| Seggarsdean Farm | Nr. Haddington (673127 35377) | 1 | 79m | 0.5MW | 0.5MW | Logan PM for Intelligent Land Investments | Application withdrawn | |
| South Belton Farm | Nr. Dunbar | 2 | 37.5m | 0.03MW | 0.06MW | Maden Design for Mr Ian Rennie | Live application (05/11/10) |
2 Hannevind 30kw turbines (Hannevind declared insolvent 21 Oct. 2011). Application Ref. 11/00411/P. Local response group: SABEL. |
| Stenton Community Turbine | Ruchlaw, West Mains, Stenton | 1 | 67m. | 0.33MW | 0.33MW | ‘Carbon Neutral Stenton’ | Application withdrawn (11/02/11) |
Enercon 33 turbine. Application Ref. 10/00615/P. Outside conservation area, nr. Pressmennan Lake and Woods. “Stenton is a community in turmoil...” (Letter). Local response group: SABEL. |
| Stonelaws Farm | Nr. East Linton | 3 | 37.5m. | 0.03MW | 0.09MW | Maden Design for Mr Colin Hunter | Live application (09/11/10) |
3 Hannevind 22/30kw turbines (Hannevind declared insolvent 21 Oct. 2011). Application Ref. 10/00914/P. Local response group: SABEL. |
| Townhead Farm | Nr. Gifford (NT551688) | 2 | 49.17m. | 0.08MW | 0.16MW | VG Energy for Townhead (McDowall) Ltd | Application withdrawn (26/10/11) |
|
| Ugston Farm | Nr. Haddington (349309 674929) |
1 | 49.17m. | 0.08MW | 0.08MW | VG Energy for Mr Robert Dykes | Deemed refusal* (15/09/11) |
*Failure to provide required EIA. ELC Planning Ref. 11/00615/P. WES 18 turbine. Local response group: SABEL. |
| Waughton | Nr. East Linton (NT568804) |
1 | 34.2m | 0.055MW | 0.055MW | TGC Renewables for landowners. | Live application (13/02/12) |
|
| West Fortune | Nr. Haddington | 1 | 60.5m. | 0.33MW | 0.33MW | PPCA Ltd for landowner | Live application (17/06/11) |
|
| West Garleton | Nr. Garleton (NT504758) |
1 | 47.5m | 0.1MW | 0.1MW | The Green Co. for landowner | Pre-application | |
| West Mains Farm | Nr. Haddington (NT574727 and NT575726) |
2 | 34.2m. | 0.05 | 0.1MW | The Green Co. for Mr Jack Russell | Refused (08/07/10) |
|
| Whittinghame Mains | Nr. Haddington E359762 N673730 |
1 | 40.4m | 0.1MW | 0.1MW | 3R Energy for Mr Michael Brander |
Refusal appealed (21/03/12) |
Appeal Ref. 12/00002/P01. Refused on landscape impacts on Traprain Law. Application Ref. 10/00767/P. Local response group: SABEL. |
| Woodhall Farm | Nr. Innerwick | 1 | 78m | 0.5MW | 0.5MW | Arcus/Temporis for Mr Macaskill | Live application (09/11/11) |
|
| Woollands | Nr. Oldhamstocks | 1 | 53m | 0.33MW | 0.33MW | GF White for Purely Scottish | Pre-application |
| Name | Place | No. | Height | Max. MW | Max. Capacity | Developer | Status | Planning Notes Response Gp. |
| Alemill Farm | Nr. Eyemouth | 1 | 62m. | 0.33MW | 0.33MW | West Coast Energy | Pre-application | Previous scoping opinion for 8 turbines 06/06/07. Screening opinion request submitted 25/08/2010 |
| Allanshaws (Shaw Park) | Nr. Stow | 9 | 99.5m. | 2.3MW | 20.7MW | Green Cat Renewables | Live Application (30/08/11) |
SBC application ref. 11/01175/FUL. Same site area as previously refused Sell Moor scheme (see above). Candidate turbine: Enercon E70. |
| Baddinsgill | Nr. West Linton (NT12280 55954) |
1 | 78m | 0.5MW | 0.5MW | Muirhall Energy for Baddinsgill WT Ltd | Live application (16/01/12) |
SBC Planning Ref. 11/01692/FUL. |
| Bairnkine | Nr. Jedburgh (E364715; N615440 & E364852 N615498) |
2 | 46.1m | 0.05MW | 0.1MW | Carleton Border Services for Mr Matthew Tile | Live application (17/01/12) |
SBC Planning Ref. 12/00030/FUL. Endurance E3120 turbine proposed. |
| Land SE Of Barnside Farm | Abbey St Bathens (NT756614) | 1 | 54m | 0.25MW | 0.25MW | Greenviro for Mr James Dobie | Application withdrawn (22/09/2011) |
SBC. Application Ref. 11/00316/FUL. See also application at Weirburn House ASB. |
| Barrel Law | Nr. Ashkirk (NT417179) |
10 | 125m | 3MW | 30MW | ABO Wind | PAN lodged (07/07/11) |
PAN ref. 11/00976/PAN. “Scoping Opinion provided 25/02/11”. Exhibitons held 09/11. |
| Bassendean Hill Farm | Nr. Gordon (NT624463) |
1 | 77m | 0.5MW | 0.5MW | Amec for Mr Roddam Home | Live application (10.08.11) |
|
| Birkenside Farm | Birkenside Farm, Nr. Earlston (E356860 N642751) |
1 | 36.2m | 0.05MW | 0.05MW | Carleton Border services for AS Hogg & Parners | Live application (02/02/2012) |
Revised application (from 54m). SBC Planning Ref. No. 12/00109/FUL. |
| Birneyknowe | Nr. Bonchester Bridge | 20 | ?125m (80m to hub) |
?MW | ?MW | Banks (not on website) |
Pre-application | Nos. have already risen from 14 to 20! See: ‘Wind farm vision for Bonchester site rises to 20 turbines’, Southern Reporter, 4 April 2012. |
| Blackburn Farm | Blackburn Farm, nr. Grantshouse (NT767672) |
6 | 126.5m. | 2.3MW | 13.8MW | Volkswind | Live application (28/07/11) |
|
| Blackhouse Farm | Blackhouse Farm, Reston (NT826601) |
1 | 70m. | 0.5MW | 0.5MW | Locogen for WB & AG Swan | Refused (27/10/11) Appealed |
SBC Planning Ref. No. 11/00674/FUL Gamesa G52 turbine. |
| Black Hill | Nr. Duns (NT728562) |
22 | 78m. | 1.3MW | 28.6MW | RES | Operational (02/07) |
Siemens SWT 1.3 turbines.
Black Hill WF - A, R00076SQSC (22T, 28.6MW): 2006/7 MWh/ROCs:28,069 2007/8 MWh/ROCs:82,151; LF:32.7% 2008/9 MWh/ROCs:76,685; LF:30.6% 2009/10 MWh/ROCs:69,571; LF:27.8% 2010/11 MWh/ROCs:51,829 Rolling LF:30.0% |
| Blackmains | Nr. Reston (NT900631) |
7 | 125m | 3MW | 21MW | Enertrag | Pre-application | Enertrag submitted a request for Scoping Opinion to SBC on 28/06/11. Preliminary exhbiitions held. Response Group: Oppose Blackmains |
| Blaewearie | Blackhaugh Farm, nr. Clovenfords (341 639) |
6 | 110m. | 2MW | 12MW | Lomond Energy/Arcus for Mr Andrew Elliot, Blackhaugh Farm | Pre-application | Scoping opinion requested from SBC, 07/10/10 (available on SBC website). LE Scoping Report (6.21Mb PDF file). 60m anem. mast approved (11/02/10). |
| Blue Cairn Farm | Nr. Galashiels (NT531421) |
1 | 47.1m | 0.1MW | 0.1MW | 3R Energy Solutions for G W & K L M Weir | Live application (21/06/11) |
SBC Planning Ref. 11/00868/FUL. |
| Bogangreen Cottages | Nr. Eyemouth (NT891664) |
1 | 30.3m | 0.03MW | 0.03MW | Maden Design for Mr Alan Henry | Consented (08/03/2011) |
Hannevind turbine (Hannevind declared insolvent 21 Oct. 2011). SBC Application No. 10/01605/FUL. Turbine collapsed 13 Dec. 2011 to ensure public safety after brake failure, 2 weeks after comissioning. Hannevind declared insolvent 21 Oct. 2011. |
| Border Precision Services | Pinnacle Hill Ind. Est., Kelso | 1 | 70m. | 0.85MW | 0.85MW | Wind Direct | Consented (20/02/08) |
Refusal recommended by PO on grounds of visual impact.
|
| Emly Bank (Bowbeat) | Peebles (NT285475) |
12 | 76m. | 1.3MW | 15.6MW | E.ON UK | Operating (2001) | Appl. 00/00371/FUL, appr. 25/09/2000
Nordex N60 turbines. Emly Bank, R00020SQSC (12T, 15MW): 2002/3 MWh/ROCs:21,243; 2003/4 MWh/ROCs:33,418; 2004/5 MWh/ROCs:35,737; LF:27.2% 2005/6 MWh/ROCs:34,595; LF:26.3% 2006/7 MWh/ROCs:37,995; LF:28.9% 2007/8 MWh/ROCs:34,699; LF:26.3% 2008/9 MWh/ROCs:35,373; LF:26.9% 2009/10 MWh/ROCs:32,001; LF:24.4% 2010/11 MWh/ROCs:26,689; LF:20.3% Rolling LF:26.2% |
| Roughside Hill(Bowbeat) | nr. Peebles (NT285475) |
12 | 76m. | 1.3MW | 15.6MW | E.ON UK | Operating | Appl. 00/00371/FUL, appr. 25/09/2000
Nordex N60 turbines. Roughside Hill, R00019SQSC (12T, 15MW): 2002/3 MWh/ROCs:21,022 ; 2003/4 MWh/ROCs:34,153; 2004/5 MWh/ROCs:36,372; LF:27.7% 2005/6 MWh/ROCs:35,184; LF:26.8% 2006/7 MWh/ROCs:38,028; LF:28.9% 2007/8 MWh/ROCs:41,379; LF:31.4% 2008/9 MWh/ROCs:35,892; LF:27.3% 2009/10 MWh/ROCs:32,078; LF:24.4% 2010/11 MWh/ROCs:26,147; LF:19.9% Rolling LF:27.1 % |
| Bowbeat Extension | Nr. Eddleston (NT288473) | 1 (5) | 110m. | 2.3MW | 2.3MW (12.5MW) | E.ON UK | Pre-application | 1 turbine in SB. 4 in Midlothian.
Scoping opinion provided 01.08.08 (available on SBC website). |
| Broadmeadows | Yarrowford, nr. Selkirk (NT410315) |
8 | 112m | 2.5MW | 20MW | Green Power | Refusal confirmed at appeal (01/12) |
Appeal rejected. Unanimous refusal by councillors, following planning officer’s advice, (13/06/11). Response group: Broadmeadows Action Group |
| Brockholes | Brockholes Farm, nr. Grantshouse (NT814632) |
3 | 56m. | 0.9MW | 2.7MW | Green Cat Renewables for Mr J Prentice |
Consented (12.05.10) |
Reduced height turbines approved despite many objections. Planning officer recommended approval. Further development creep out from “Lammermuirs Wind farm landscape”. |
| Brunta Hill | Nr. Westruther (NT597514) |
10 | 126.5m | 3MW | 30MW | PNE Wind | Live Application (20/10/11) |
|
| Bushelhill Farm | Nr. Monynut Edge & Aikengall II | 1 | 100m | 2.3MW | 2.3MW | SAC Consulting for Mr Shell | Pre-application | Two possible sites: Corse Hill, Black Hill. SBC: “Screening opinion request – circulated to internal consultees & East Lothian Council 8/10/10”. Response group: Save the Lammermuirs (STL) |
| Buskin Farm | Nr. Eyemouth (NT879671) |
2 | 30.3m | 0.03MW | 0.06MW | Maden Design for Mr Peter Wright | Consented (14/01/2011) |
|
| Carcant | Nr. Heriot (NT362528) |
3 | 107m. | 2.3MW | 6.9MW | Airtricity | Operational (06/10) |
Siemens 2.3 turbines. Airtricity acquired from AMEC. Consented 09.06 |
| Carlops Hill Farm (South Mains) |
Nr. West Linton (NT169552) |
1 | 86.5m | 0.8MW | 0.85MW | Locogen for Mr John Aitken | Live application (22/09/11) |
SBC planning Ref. 11/01282/FUL. Enercon E53 turbine proposed. |
| Castle Mains | Nr. Duns (NT756562) |
3 | 47m | 0.1MW | 0.1MW | The Green company for Mr Wilson Nimmo | Live application (17/08/11) |
SBC Ref. 11/01086/FUL. |
| Clockmill Farm/NW Of Cedar Cottage | Nr. Duns (E376558 N654351) |
1 | 66.79m | 0.25MW | 0.25MW | George F White for Mr A J Hodge | Live application (15/06/11) |
SBC Ref. 11/00796/FUL. |
| Clockmill Farm/NW Of Cedar Cottage | Nr. Duns (E376518 N654336, E376604 N654255) |
2 | 34.4m | 0.05MW | 0.05MW | George F White for Mr A J Hodge | Live application (17/04/12) |
SBC Ref. 12/00453/FUL. Endurance E3120 turbine proposed. |
| Cloich Forest | Nr. Eddleston (NT207480) |
24 | 130m. | 2.5MW | 60MW | Partnership for Renewables for Forestry Commission Scotland | Pre-application | |
| Cathpair | Nr. Stow | 15 | 110m | 2.5MW | 37.5MW | Lomond Energy | PAN lodged | |
| Clyde Extension | Nr. Biggar | 7 (57) | 142m. | 3MW | 21MW (171MW) | SSE website | Live application(11/10/2011) | Section 36 application (over 50MW). Following fast on consented 152 turbines, not yet operational. some 7 of 57 in SBC area. See ECU website. |
| Coldstream Mains | Nr. Coldstream (NT840418) |
1 | 53m | 0.33MW | 0.33MW | Mr & Mrs C MacGregor | Not pursued. | SBC. “Screening Opinion requested 12 April 2010 (provided 27 April 2010)”. |
| Corbie Shank, Craik Forest | Craik Forest, nr. Hawick (NT337007) |
73 | N/A | ca. 150MW | REC Ltd. | Pre-application | SBC. Sect 36 scoping opinion provided 08.04.03 |
|
| Corsbie Moor | Nr. Legerwood (NT599456) |
12 | 126.5m | 2.3MW | 27.6MW | E.ON UK Renewables. | Live application (30/08/10) |
|
| Cothill Farm | “NE of Kirkburn Hse.”, Nr. Greenlaw () |
1 | 40m | 0.05MW | 0.05MW | Enviko Ltd for Mr David Seed | Live Application (05/03/2012) |
SBC Application Ref. 12/00267/FUL. C & F CF50 Turbine. |
| Cowieslinn | Nr. Eddleston | 2 | 80m | ?MW | ?MW | WhiteRock Energy Ltd | Pre-application | SBC Screening Opinion (PDF download) supplied 26/05/11. 60m anem. mast approved (11/00770/FUL), 26/08/2011. |
| Crosslaw Farm | Nr. Coldingham | 2 | 30m | 0.03MW | 0.06MW | Maden Design for Mr Douglas Allan | Consented (14/01/2011) |
|
| Crystal Rig - ‘Phase 1’ | (NT678678) | 20 | 100m. | 2.5MW | 50MW | Fred Olsen Renewables/ Natural Power |
Operating (2003) | Appl 01/00269/FUL, appr. 10.09.01
Site in AGLV. Extension & C.R. Phase 2 consented, see below. Crystal Rig WF - A,E, R00049SQSC (20T, 50MW): 2003/4 MWh/ROCs:7,224 2004/5 MWh/ROCs:113,835; LF:26.0% 2005/6 MWh/ROCs:107,435; LF:24.5% 2006/7 MWh/ROCs:119,129; LF:27.2% 2007/8 MWh/ROCs:106,390; LF:24.2% 2008/9 MWh/ROCs:114,342; LF:26.1% 2009/10 MWh/ROCs:124,310; LF:28.4% 2010/11 MWh/ROCs:102,057 Rolling LF:25.8% |
| Crystal Rig - ‘Phase 1a’. | (NT660690) | 5 | 125m. | 2.5MW | 12.5MW | Fred Olsen Renewables/ Natural Power |
Operational (05/07) |
Nordex N80 turbines. Site in AGLV. |
| Crystal Rig - ‘Phase 2’ | (NT678678) | 23 (52) | 30x110m 22x125m. |
128.8MW | Fred Olsen Renewables/ Natural Power |
Operational (09/09/10) |
Section 36 appl. 01.05.04, 23 Turbines in Sc. Borders, 29 in East Lothian.
Further 9 (‘Phase IIa’) in East Lothian. Site in AGLV. Crystal Rig II WF, R00103SQSC (60T, 135.365MW): 2009/10 MWh/ROCs:14,996; 2010/11 MWh/ROCs:299,908; LF:24.8% Rolling LF:23.2% |
|
| Cummings Hill | Nr. Chesters, Hawick | 13 | 100m | 2MW | 26MW | Infinis | PAN lodged. | 60m anem. mast approved (12/09/11). Community response group: Chesters Wind Farm Action Group (no contact details). |
| Denholm Hill | Nr. Hawick | 2 | 70m | ? | ? | Fingleton White for landowner | Pre-application | SBC Screening request. |
| Dere Street | Nr. Dun Law | 6 | 91m | ? | ? | Pegasus Planning Group | Pre-application | SBC Scoping response, 2 February 2011. Close to existing Dun Law sites. Concern re. cumulation and impacts on ancient monuments at Soutra Aisle and Dere Street, which crosses the site area. |
| Ditcher Law | Nr. Oxton (NT509568) |
? | ? | ? | ? | Dawn Energy | Pre-application | |
| Dowlaw Farm | Nr. St Abbs (NT855700) |
2 | 30m | 0.03MW | 0.06MW | Maden Design for Mr Ian Russell | Consented (19/09/11) |
SBC Application Ref. No. 11/00928/FUL. Hannevind 30kw tubines (Hannevind declared insolvent 21 Oct. 2011). |
| Drone Hill/Coldingham Moor | Nr. Coldingham (NT840676) | 22 | 76m. | 1.3MW | 28.6MW | PM Renewables/Your Energy Website |
Under construction | SBC Appl. No. 05/00425/FUL. Unan. refusal by LPA (following officer advice). Consented on appeal, November 2008: Appeal Decision Notice. |
| Dunion Hill | Nr. Denholm & Jedburgh (NT613172) |
8 | 101m. | 2.3MW | 18.4MW | Windjen Power | Refused at appeal. | Appl. No. 05/02336/FUL, 13.01.06. Refused SBC 10.09.07. Refused on appeal 9.04.09 (first refusal on appeal for SBC). See Appeal decision notice. Dunion Hill Conservation Group |
| Dun Law (Soutra) |
Nr. Soutra (NT466573) |
26 | 63.5m | 0.66MW | 17.16MW | RES for Sc. Power |
Operational (2000) | RES for Scottish Power Renewables (owned by Iberdrola Renewables). Appl. No. 96/01130/FUL. Appr. 31.07.97 Vestas V47 0.66MW turbines. SRO Dun Law - A, R00009SQSC (26T, 17.16MW): 2002/3 MWh/ROCs:33,985; LF:22.6% 2003/4 MWh/ROCs:42,520; LF:28.2% 2004/5 MWh/ROCs:42,047; LF:28.0% 2005/6 MWh/ROCs:38,166; LF:25.4% 2006/7 MWh/ROCs:42,772; LF:28.5% 2007/8 MWh/ROCs:33,232; LF:22.0% 2008/9 MWh/ROCs:40,283; LF:26.8% 2009/10 MWh/ROCs:32,376; LF:21.5% 2010/11 MWh/ROCs:29,652; LF:19.7% Rolling LF:25.2 % |
| Dun Law 2 (Soutra) |
Nr. Soutra (NT484585) |
35 | 75m | 0.85MW | 29.75MW | RES for Sc. Power |
Operational (10/09) |
Consented 09/07. Vestas V52 turbines. Scottish Power Renewables (owned by Iberdrola Renewables). Dun Law Extension, R00125SQSC (35T, 29.75MW): 2009/10 MWh/ROCs:43,945; 2010/11 MWh/ROCs:57,798; LF:22.2% Rolling LF:22.6% |
| Earlshaugh | Nr. Moffat (NT080155) |
24 | 125m. | “3MW | 72MW | Wind Energy Ltd | Resubmission (08/11). |
Section 36 Application July 2008. SBC objected (Nov. 2008). Turbines reduced to 24 from 36, resubmission to Scottish Govt. ECU. Local response group: (SOS) Save Our Scenery |
| Easter Housebyres | Easter Housebyres, nr. Melrose (NT53 37) |
6 | 80m | 1.3MW | 7.8MW | Energy4All Scotland | Pre-application | SBC. Scoping opinion provided 25.03.10 (available on SBC website). |
| Easter Howlaws | Nr. Greenlaw (642860/371752 & 642792/371811) |
2 | 47.1m. | 0.1MW | 0.2MW | Segen Ltd. for Mr Mervyn Wallace | 1 Built & Operating (11/11) |
Delegated decision, consented despite proximity to Hume Castle and SBC’s own SPG. Application Ref. No. 10/01536/FUL. Northwind 100 turbines. |
| Eastlaw House | Nr. Coldingham (NT911656) |
1 | 34.2m | 0.05MW | 0.05MW | Maden Design for Mr John White | Application withdrawn (10/11/11) |
SBC Planning Ref. 11/01117/FUL. |
| Edington Mains | Nr. Foulden (NT90245615) |
1 | 86.5m. | 0.8MW | 0.8MW | Locogen for landowner | Pre-application | Screening opinion request 3.2.11. |
| Fala Hill | Nr. Heriot | 3 | 101m. | 2.3MW | 6.9MW | E.ON.UK | Refused | Appl. No. 04/02420/FUL. Refused SBC 8/5/06. |
| Fallago Rig/Ridge Mk. II | Nr. Longformacus (NT570680) |
48 | 100 & 125m. | 3MW | 144MW | North British Windpower (NBW) | Under construction (9/11/10) |
Decision letter. Section 36 Application 16.05.05 (Mk. I). Mk. II - numbers reduced from 62 to 48 (01/07). SBC objection 05.02/07 PI held in 2008 and re-opened to hear new evidence (mainly on MOD radar) in 2010. Judicial review failed May 2011. Response group: Save the Lammermuirs (STL). Site owned by the Duke of Roxburghe. |
| Falla Knowe Farm | Nr. Coldingham (E361687 N642489). |
1 | 45.9m. | 0.225MW | 0.225MW | Mr Andrew Hughes | Live application (24/04/12) |
SBC Application Ref. 12/00503/FUL. ACSA A27 turbine proposed. |
| Fellowhills | Nr. Ladykirk (NT888491) |
1 | 45.2m | 54m0.225MW | 0.225MW | Carleton Border Services for Mr Ian Martin, Galagate Farms. | Live application (17/04/12) |
SBC Planning Ref. 12/00482/FUL.Previous application (11/01476/FUL) for 54m turbine withdrawn (14/12/11). Norwin 30/225kW. |
| Forth Array (Offshore) |
17km off St Abbs Head | 70-90 | 163m | 5MW | 415MW | Unclear | “Options for this developer selected site will be reviewed by The Crown Estate”. see: ‘Fred Olsen Quit Forth Array’. (UK Offshore Wind, 19 Nov 2010). |
|
| Frogden Farm | Nr. Kelso | 9 | 100m. | 1.5MW | 13.5MW | Wind Hydrogen Ltd. | Pre-application | Scoping opinion provided 24/10/07 (available on SBC website). |
| Gattonside Mains | Nr. Gattonside (635392 352753) |
1 | 54m | 0.25MW | 0.25MW | Carleton Border Services for JSC Partnership Ltd (Pavilion Estate) | Application Withdrawn (02/09/11) |
SBC Application Ref. No. 11/00938/FUL. WES30 tubine. |
| Gilston (Brotherstone) | Nr. Gilston | 7 | 115m | 2MW | 14MW | Ridgewind | Live Application (10/01/12) |
SBC planning ref. 11/01680/FUL |
| Girthgate | Whitlaw Farm, Nr. Lauder | 20 | 130m | 3MW | 60MW | Community Windpower | Pre-application | Will be decided by Scottish Government (over 50MW). 50m anem. mast application in (11/00904/FUL). Community response group: LPG - Lauderdale Preservation Group. |
| Glenkerie (Kingledores) | Nr. Tweedsmuir (NT092279). |
11 | 6 x 105m. 5 x 120m. |
1.8-2.5MW | 19.8-27.5MW | Infinis (Novera) | Under construction | SBC appl. no. 07/02478/FUL. Appr. SBC: 08/09/08; Appr. Scottish Exec. 27/10/08; Final Appr. 10/09/09. |
| Greenburn Farm | Nr. Reston (NT839612) |
1 | 54m | 0.25MW | 0.25MW | Greenviro for Mr W Mole | Live application (18/03/2011) |
SBC Application Ref. No. 11/00315/FUL |
| Greenvale | Craigswalls, Chirnside (NGR 845 558) |
1 | 130m | 2.5MW | 2.5MW | Greenvale (Wind Direct) |
Pre-application | SBC. “Scoping Opinion requested 22 April 2010 (provided 25 May 2010)”. |
| Hawick | Nr. Pilmuir, Hawick | ? | ?m. | ? | ?MW | ? | Pre-application | On Common Good Land near Williestruther Loch. Proposed by ‘A Greener Hawick’ (see ‘Ill wind blows over turbine site proposal’, Hawick News, 11.02.10). Talks ongoing a/o 20/10/11. |
| Haystoun House | Nr. Peebles | 1 | 61m. | 0.33MW | 0.33MW | Mr David Coltman | Refused | Enercon E33 turbine; appl. for 20m turbine also refused. |
| Heathpool | Nr. Eddleston (NT255455) |
6-7 | 60-70m hub | ? | Ridge Wind | Pre-application | “Pre-scoping opinion discussions, no scoping opinion requested”. |
|
| Hexpath Farm | Nr.Greenlaw | 1 | 76m | 0.5MW | 0.5MW | Arcus for landowner | Pre-application | SBC scoping opinion supplied 10/05/11. |
| Hillhouse | Nr. Oxton (NT490572) |
6/11 | ?76m | ? | Mr Sutherland | Pre-application | “Opinion requested April 2010.” “Scheme 1; 6 Turbines, 76m to blade tip; Scheme 2: 11 turbines.” Response group: Save the Lammermuirs (STL) |
|
| Hoprigshiels | Nr. Oldhamstocks | 3 | 80m | 2.5MW | 7.5MW | ENTEC for BHA/CES | Live application (06/06/11) |
SBC Planning Ref. 11/00664/FUL. Fund-raising enterprise by Berwickshire Housing Association (2/3), Community Energy Scotland (1/3). Response group: Save the Lammermuirs (STL) |
| Horn Burn | Nr. Ayton | 10 | 115m | 2MW | 20MW | Energiekontor | Pre-application | Preliminary exhibitions: Reston Vill. Hall 29 Feb. 3-8pm. Ayton Comm. Hall 1 March, 3-8pm. SBC state that, “we have not received a Screening or Scoping Opinion for this site” (12/02/12). Response Group - see: Oppose Blackmains. |
| Hyndfordwell Farm | Nr. West Linton (NT140484) |
1 | 39.9m | 0.08MW | 0.08MW | W G & E M Harrison | Refused (06/07/11) |
First application “...refused on the grounds of landscape impact and MoD objection.”. Subsequent appl. for 3x27m turbines withdrawn. SBC Application No. 11/00217/FUL. |
| Hyndhope/W Alemoor (Langhope Rig Extension) |
Nr. Hyndhope. | 10-15 | 125m. | ?MW | ?MW | Natural Power Consultants | Pre-application | SBC scoping opinion provided 24.02.09 (available on SBC website). |
| Kelloe Mains | Nr. Duns (NT840542) |
1 | 66.7m | 0.33MW | 0.33MW | SAC Commercial for R & J MacDonald | Refused | Application refused and confirmed at review, 20/7/11 (visual impacts). Enercon E33 turbine. |
| Kinegar Quarry | ‘SW of Neuk Farm’, Nr. Cockburnspath (NT376376 669840) |
2 | 110m. | 2.5MW | 5MW) | S R Findlay Wind Direct |
Live application. (29/02/12) Resubmission. |
Resubmission: Appl. No. 12/00221/FUL. Original Appl. for 2 x 130m turbines: 10/00364/FUL. Refused (15/09/10), review confirmed (21/02/11). |
| Langhope Rig | Nr. Ashkirk (NT406203) |
10 | 121.2m | 2.3MW | 23MW | Formerly Airtricity, acquired by SSE | Consented (05/08) |
SBC Appl. No. 06/01236FUL. Appl. Refused 07.07. Consented on appeal 05.08. Construction still not started as of May 2011. |
| Langshaw | Nr. Galashiels | 1 | 39.5m. | 0.05MW | 0.05MW | Martyn Bergius | Operating | Consented 23.11.09. SBC Appl. No. 09/01140/FUL. |
| Lanton Crags | Nr. Jedburgh (363110 620712) |
1 | 66.6mm | 0.33MW | 0.33MW | Green Cat for Mr Alec Riding | Application withdrawn (02/11) |
SBC Application No. 10/01489/FUL. “The application was withdrawn because the [SBC] planning officer indicated that it would be turned down on two grounds: firstly because of the MOD’s objections [seismic interference], but also because of the perceived landscape and visual impact.” (Southern Reporter, 17/02/11) |
| Leithope | Nr. Carter Bar (NT715095) |
32 | 115m. | 2.18MW | 70MW | Npower | Pre-application | SBC Sect 36 scoping opinion provided 22.12.05 (available on SBC website). |
| Lintlaw Farm | Nr. Duns (NT81855799) |
2 | 31.5m & 37.5m | 0.03MW & 0.022MW | 0.052MW | Mr Ian Calder | Consented (25/03/2011) |
SBC. Planninp Ref. No. 11/00095/FUL. Only 150m from curtilage of cottages. |
| Long Park (Halkburn) | Nr. Stow (NT480420) |
19 | 110m. | 2MW | 38MW | Wind Prospect | Operational (10/09) |
Refused SBC (31/8/05), landscape impacts. Consented on appeal: Appeal Decision Notice. REpower MM82 turbines. Longpark WF, R00119SQSC (19T, 38MW): 2009/10 MWh/ROCs:43,244; 2010/11 MWh/ROCs:67,284; LF:20.2% Rolling LF:20.3 % |
| Lumsdaine Farm | Nr. Coldingham |
2 | 30.3m. | 0.03MW | 0.06MW | Maden Design for Mr James Fullarton | Consented (14/2/11) |
Hannevind 30Kw turbines (Hannevind declared insolvent 21 Oct. 2011). Application Ref. No. 10/01654/FUL . |
| Middle Hill | Nr. Tweedsmuir | 11 | 105m | 2.45MW | 27MW | West Coast Energy | Scoped, inactive. | SBC. Scoping opinion provided 12/09/05 (available on SBC website). |
| Minch Moor | Nr. Innerleithen | 12 | 100m. | 2MW | 24MW | Vattenfall | Refused 09/08/10 Appeal refused 21/04/11 |
Application No. 03/00627/FUL, Appeal DPEA Ref. PPA-140-2021 Refused on landscape grounds. Originated by AMEC, sold to Swedish company Vattenfall. |
| Minto Farm | Nr. Denholm (552829 24141) |
1 | 71m. | 0.25MW | 0.25MW | Pre-application | SBC, “Screening Opinion issued 10/11/10”. |
|
| Monashee | 3.5km west of Grantshouse (NT801611) | 6 | 119m | 2.5MW | 17.5MW | RDS Element Power | Live application (06/04/12) |
SBC Planning Ref. 12/00431/FUL. Previously scoped and dropped by West Coast Windfarms (9/03). Response group: Save the Lammermuirs (STL). |
| Moor House Farm | Nr. Cockburnspath | 3 | 66m. | 0.33MW | 0.99MW | G F White/Drysdale | Pre-application | SBC: “EIA Screening/Scoping Opinion sent 1.11.10 – EIA not required”. Enercon E33 turbines. |
| Muircleugh | Nr. Lauder |
2 | 125m. | 2MW | 4MW | Airvolution Energy for Lauder Common Good Fund | Live application (29/11/11) (Resubmission). |
|
| Nether Huntly Wood Hse. | Nr. Gordon (E361687 N642489). |
1 | 45.9m. | 0.225MW | 0.225MW | Mr Andrew Hughes | Live application (24/04/12) |
SBC Application Ref. 12/00503/FUL. ACSA A27 turbine proposed. |
| Nethermains Farm | Nr. Chirnside | 1 | 31.9m. | 0.075MW | 0.075MW | F, ME & RN Millar | Consented (29/03/2010) |
Application Ref. No. 09/01672/FUL. Vestas V17-75 turbine. |
| Nisbet Hill Farm | Nr. Duns (NT792506) |
2 | c. 46m. | 0.225MW | 0.45MW | 1 Stop Renewables Wind Energy for landowner | Pre-application | SBC, Screening Opinion (PDF doc.), issued 03/02/11. |
| Old Cambus Quarry, Cockburnspath | Nr. Cockburnspath (NT811704) |
1 | 66m. | 0.33MW | 0.33MW | G F White for R & K Drysdale | Pre-application | SBC “EIA Screening/Scoping Opinion sent 1.11.10 – EIA requested” Enercon E33 proposed. Anem. mast consented 29/10/10, Ref. 10/01177/FUL. |
| Old Farmhouse, Townhead | Nr. Cockburnspath (NT797693) |
1 | 54m | 0.33MW | 0.33MW | Savills for Windberry Energy Operations | Live application (13/10/11) |
SBC. Planning Ref. 11/01392/FUL. Enercon E33 turbine proposed. |
| Over Langshaw Farm | Nr. Galashiels | 1 | 39.5m. | 0.05MW | 0.05MW | Laurence Gould Partnership for Martyn Bergius | Consented (23.11.2009) |
Application Ref. No. 09/01140/FUL. |
| Overwells Farm | Nr. Jedburgh (368064,621016) |
1 | 40.2m | 0.05MW | 0.05MW | Carlton Border Services for Mr Patrick Fraser | Live application (01/11/11) |
SBC. Planning Ref. 11/01475/FUL. Endurance E3120 turbine proposed. Response Group: Minto Hills Conservation Group (MHCG) MHCG Email. |
| Penmanshiel Moor | Nr. Grantshouse (NT822678) |
15 | 100m | 2.5MW | 37.5W | RES | Live Application (27/10/11) |
|
| Press Mains Farm | Nr. Coldingham (NGR 886 651) |
1 | 61m. | 0.33MW | 0.33MW | Passim Developments for P & E Edmondson | Consented (16/12/2010) |
Application Ref. No. 10/00626/FUL. Enercon E33 turbine. |
| Primrosehill Farm | Nr. Preston | 2 | 67m. | 0.85MW | 1.7MW | Arcus for e-Gen | Refused (09/12/11) |
SBC Application Ref. 11/00891/FUL |
| Quixwood | Nr. Grantshouse | 14 | 125.25 | 2.5MW | 35MW | Banks Renewables | Live application (22/12/11) |
|
| Rink Farm | Nr. Galashiels (632351,348294) |
1 | c. 35m. | N/A | N/A | whichturbine.com for Messrs J M & R Bayne | Live application (27/05/11) |
SBC Application Ref. 11/00652/FUL |
| Rowantree | Nr. Fountainhall (NT465500) |
23 | 125m. | 3MW | 69MW | RWE NPower | Live application PI pending |
Section 36 application (over 50MW). Maj. SBC cllrs ignored officer’s recomm. and opposed on grounds of cum. impact, noise and effect on walking routes. Reporter appointed, PI scheduled to start at 10.00am on 5 March, 2012, Carfraemill Hotel, Oxton. Docs available at SBC HQ, 2 wks before PI begins, and on DPEA website. |
| Selkirk,North Common | Selkirk | 3 | 102m. | 2.3MW | 6.9MW | Selkirk Regeneration Co. | Pre-application | One of 3 turbine array options being considered by SRC - SRC website. SBC scoping opinion provided 24/06/09 on larger scheme (available on SBC website). £140,000 development loan by the Sc. Govt. (for possible £11K annual earnings!) |
| Sell Moor | Nr. Oxton (NT480444) |
19 | 115m. | 2.5MW | 47.5MW | RDC | Refused (31/8/05) |
Appl. No. 04/00350/FUL. |
| South Slipperfield Farm | Nr. West Linton (E3121965 N651469) |
1 | 48m | ?MW | ?MW | 3r Energy Solutions | Pre-application | SBC. “Screening opinion request 30.03.2011”. |
| Spurlens Rig | Nr. Leadburn (NT248538) |
6 | 125m | 2MW | 12MW | Lomond Energy/ Ventus VCT |
Refused (30/11/11) |
SBC Planning Ref. 10/01669/FUL. Response group: APEAL - Association to Protect the Environment at Leadburn. |
| Standhill | Nr. Denholm (NT5661022583) |
1 | 74m | 0.5MW | 0.5MW | Greenspan Agency | Live application (15/03/12) |
|
| Stuartslaw Farm | Nr. Chirnside (655501 384698). |
1 | 54m. | 0.25MW | 0.25MW | Gretna Green Group Ltd | Live application | SBC Application Ref. (available on 11/00700/FUL). WES30 turbine. |
| Sunnyside Farm | Nr. Reston (E384358 N661787). |
1 | 45.9m. | 0.225MW | 0.225MW | Intelligent Land Investments Ltd | Live application (25/04/12) |
SBC Application Ref. 12/00514/FUL. ACSA A27 turbine proposed. |
| Sunwick | Nr. Hutton | 5 | 145m | 2MW | 10MW | Veritas Energy | Pre-application | SBC. “Screening request received 18 June 2009. Opinion provided 17 July 2009.” (available on SBC website). 70m anem. mast approved 03/03/2010 (Applic. Ref. 10/00070/FUL) |
| Thirlestane Farm | Nr. Lauder (356481 648270). |
1 | 45.5m. | 0.225MW | 0.225MW | Tom Barr | Live application | SBC Application Ref. 11/00913/FUL). ACSA A27 turbine. |
| Toddleburn | Nr. Oxton (NT450531) |
12 | 110m. & 125m. | 2.3MW | 27.6MW | SSE | Operational (06/10) |
Siemens 2.3 turbines. Refused SBC (31/8/05)- landscape impacts. Consented on appeal (01.07): Appeal Decision Notice. Toddleburn WF, R00120SQSC (12T, 27.6MW): 2009/10 MWh/ROCs:6,034 ; 2010/11 MWh/ROCs:58,081; LF:24.0% Rolling LF:24.3% |
| Upper Kidston Farm | Nr. Peebles (NT224424) |
Max. 10 | ? | ? | Volkswind | Pre-application | SBC. “Pre-scoping opinion discussions, no scoping opinion requested”. |
|
| Wauchope Forest | Nr. Hawick | ? | ?m. | ?MW | ?MW | Partnership for Renewables for FCS | Pre-application | PFR for Forestry Commission Scotland. “Including - Hyndlee, Lethem, Peel, Shankend, Whitrope” (Press release). |
| Land NE of Weirburn House | Abbey St Bathens (NT770618) | 2 | 54m | 0.25MW | 0.50MW | Greenviro for Mr William Dobie | Approved (18/11/11) |
SBC. Application Ref. 11/00314/FUL. |
| Wester Housebyres | Nr. Melrose | 1 | 67m. | 0.33MW | 0.33MW | Green Cat for landowner | Pre-application | SBC “Screening opinion provided 24/12/10” |
| West Mains | Nr. Lauder | 1 | 33.6m | MW | MW | Mark Runciman | Live Application (23/03/2012) |
SBC Application Ref. 12/00323/FUL. |
| Whim Moss | Lamancha, Nr. West Linton | 3 | 100m | 1.5MW | 4.5MW | West Coast Energy | Pre-application | “Screening opinion issued 4th May 2011.”. |
| Whiterig | Nr. Lamberton (NT949584) |
2 | 45m. | ?MW | ?MW | Locogen for Tellus Energy | Pre-application | SBC Screening opinion (12/00525/SCR) sought, 16/04/12. |
| Whitmuir Farm | Nr. Lamancha (NT197508 ) |
1 | 34.2m | 0.05MW | 0.05MW | Mrs H Anderson Whitmuir Organics |
Live Application (09/06/2011) |
SBC Application Ref. 11/00787/FUL. Endurance 50Kw turbine proposed. Three 15.5m turbines already approved (25/02/11). |
| Whitslaid Farm | Nr. Lauder | 2 | 37.58m | 0.03MW; | 0.06MW | Maden Design for Mr Douglas Younger | Operational | Consented (08/02/2011). SBC Application No. 10/01382/FUL Hannevind 14D 30kW turbine. Hannevind declared insolvent 21 Oct. 2011. |
| Whitton | Nr. Morebattle (NT748207). |
6 | 110m. | “up to 3MW” | up to 18MW | Vattenfall | Live application. | SBC Appl. No. 09/01162/FUL. You can comment online on the application. Project originated by AMEC, sold to Vattenfall. 70m anem. mast approved (01/11/11). Local response group: Protect Your Cheviots. |
| Windshiel Farm | Nr. Duns | 1 | 66.6m. | 0.33MW | 0.33MW | Savills for landowner | Pre-application | SBC Screening opinion sought 04/07/11. |
| Windy Edge | Braidlee & Sundhope farms, nr. Newcastleton | 20 | 125m | ? | ? | Infinis | PAN lodged | On hold for 6 months (14/04/12). (WF moratorium - Eskdalemuir seismic monitoring station). SBC scoping opinion (08/07/11). Response group: Windy Edge Wind Farm Community Liaison Group. |
| Windy Law | Nr. Oxton (NT523581) |
? | ? | ? | ? | Dawn Energy | Pre-application | |
| Woodend Farm | Nr. Gavinton (NT75585134) |
1 | 34.2m | 0.05MW | 0.05MW | Richard Amos Ltd for Mr John Seed | Refused (19/01/12) |
SBC Planning Ref. 11/00849/FUL. Endurance E-3120 turbine. |
| Woodheads Farm | Nr. Polworth, Greenlaw | 1 | 40.2m | 0.05MW | 0.05MW | Carleton Border Services for Mr Gary Davison | Live application (19/12/11) |
SBC planning ref. 11/01652/FUL. Endurance E-3120 turbine planned. |
| Yetholm - Loch Tower Farm | Nr. Yetholm (E380998 N627070). |
2 | 45m. | 0.25MW | 0.50MW | Carleton Border Services for Mr James Wauchope | Live application(20/03/12) | |
| Yetholm Mains | Yetholm (NT839291/NT836281) |
2 | 71m | 0.275MW | 0.55MW | Fisher German | Pre-application | SBC Screening opinion (01/4/11) |
Every effort has been taken to ensure that the information published on this web site is accurate. However, windbyte.co.uk can accept no liability for the accuracy of content which has been gathered from other published sources. Visitors who rely on this information do so entirely at their own risk.
If you find any errors - please email corrections to the webmaster.